EVM in Practice. Strategic Control throughout Project Life Cycle. Peerapong Aramvareekul, Ph.D., PMP, PSP, EVP Ronnie D. Stephens

Similar documents
GAO Earned Value Management (EVM) Audit Findings

EARNED VALUE MANAGEMENT WHAT IS IT AND WHY SHOULD I CARE?

Advanced Uses of Earned Value Management in Projects, Programmes and Portfolios

PARCA. DoD EVM Policy Initiatives. Mr. John McGregor PARCA Deputy Director for EVM. NDIA IPMD Meeting August 29, 2018

Using Earned Value in Scientific Research. David Roberts & Sheila Roberts CUPE International.

Earned Value Management Practitioners Symposium

Lessons learned from implementing EVM on a large scale IT portfolio at the Department of State

The EVM + AGILE Anthology

Applicability of Earn Value Management in Sri Lankan Construction Projects

EVM for the Rest of Us

... I Poge1of4 I... Next

Click to edit Master title style

DoD EVM POLICY Using EVM and Agile Together

Creating Strategic Capital for EVM. EVA th June 2012 Andrew Hill PROJECT CONTROLS CONSULTING

From Bid Package to Detailed EVM Baseline in One Easy Step, Can it be Done?

Critical Success Factors for Earned Value Analysis in Managing Construction Projects 1, 2

EVM Practice & Future Trend

MEASUREMENT WHO NEEDS IT?!! Walt Lipke PMI - Oklahoma City

Application of EVM to Contracts

Earned Value Management ASMC Regional PDI Hanscom AFB

Introduction Methods to Track Changes in Cobra Cobra Project Preferences Cobra New Feature Change Log Summary

From the CEVM. Department of the Navy (DON) Earned Value Management (EVM) Quarterly Newsletter. October Inside this issue:

RECOLLECTIONS OF A PROGRAM MANAGER

Surveillance. Mariano Ramos Chargé de Mission OIE Programmes Department

DoD EVM. EVM Requirements, Application, Reporting, & Execution. Mr. John McGregor PARCA Director for EVM. David Nelson Karen Kostelnik

THE USE OF EARNED VALUE MANAGEMENT FOR INITIATING DIRECTIVE PROJECT CONTROL DECISIONS: A CASE STUDY

Earned Value & Project Management. Bill Simpson Marshall Space Flight Center NASA EVM Primary Center May 15, 2003

Steve Wake Chairman Association for Project Management UK. Slide 1

Project Duration Forecasting

Promoting One Health : the international perspective OIE

Robert Bob Rovinsky 2018 Project Management Symposium

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

Terms of Reference (TOR) for a Short term assignment. Policy and Legal Advice Centre (PLAC), Serbia

Economic impact of financing PVS Gap Analysis. Franck C.J. Berthe OIE Biological Standards Commission WB Food and Agriculture Global Practice

Managing AMR at the Human-Animal Interface. OIE Contributions to the AMR Global Action Plan

Stray Dog Population Control

RESTRAINING SYSTEMS FOR BOVINE ANIMALS SLAUGHTERED WITHOUT STUNNING WELFARE AND SOCIO-ECONOMIC IMPLICATIONS

Strengthening capacity for the implementation of One Health in Viet Nam, Phase 2 (SCOH2) TERMS OF REFERENCE

OIE STANDARDS ON VETERINARY SERVICES ( ), COMMUNICATION (3.3), & LEGISLATION (3.4)

(L)earned Value Janis Rizzuto (April 13, 2006)

Effective Vaccine Management Initiative

o VETERINARY IMMUNODIAGNOSTICS MARKET- GLOBAL OPPORTUNITY ANALYSIS AND INDUSTRY FORECASTS TO 2022 Report ID: MRAM Publishing Date: July, 2017

Investing in Human Resources in Veterinary Services

Strategies for Improved Earned Value Management Use by Defense Business Leaders

GOOD GOVERNANCE OF VETERINARY SERVICES AND THE OIE PVS PATHWAY

OIE Standards on Animal Welfare, and Capacity Building Tools and Activities to Support their Implementation

Inaugural Annual Letter 2019

STRAY DOG POPULATION CONTROL TERRESTRIAL ANIMAL HEALTH CODE CHAPTER 7.7.

COMPANY PRESENTATION

2013 AVMA Veterinary Workforce Summit. Workforce Research Plan Details

International Harmonisation in the Field of Pharmacovigilance from an OIE perspective

MIDDLE EAST REGIONAL ANIMAL WELFARE STRATEGY

Questions and Answers on the Community Animal Health Policy

THE ECONOMIC IMPACT OF THE OSTRICH INDUSTRY IN INDIANA. Dept. of Agricultural Economics. Purdue University

OIE SUB-REGIONAL TRAINING SEMINAR ON VETERINARY LEGISLATION FOR OIE FOCAL POINTS

Outcomes of AVSBN 2017

Building Competence and Confidence. The OIE PVS Pathway

The Center for Animal Health in Appalachia (CAHA)

The PVS Tool. Part 4. Introduction to the concept of Fundamental Components and Critical Competencies

The U.S. Department of Defense s Earned Value Management Analyst Workforce

Case Study: SAP Implementation in Poultry (Hatcheries) Industry

Dogs and Cats Online All of our Puppies in One Basket

OIE activities on rabies: PVS, vaccine banks and the OIE twinning

Strategy 2020 Final Report March 2017

Overview of the OIE PVS Pathway

Kennelbuild. The professional Kennel specialists PROFESSIONAL KENNELS FOR WORKING DOGS, VETS AND ANIMAL CHARITIES CONSULTANCY DESIGN PLANNING SUPPLY

The South African AMR strategy. 3 rd Annual Regulatory Workshop Gavin Steel Sector wide Procurement National Department of Health; South Africa

Dr Elisabeth Erlacher Vindel Head of Science and New Technologies Departement OIE AMR strategy and activities related to animal health

OIE strategy on AMR and the Prudent Use of Antimicrobials

Welcome to Texas. What is this? 2018 American Society of Health-System Pharmacists Page 1 of 13

The Philippine Action Plan to Combat Antimicrobial Resistance: One Health Approach

Kumeu/Huapai Waitakere to Swanson Public Transport Options

First-year experiences in implementing Thailand s National Strategic Plan on AMR

WHO perspective on antimicrobial resistance

WhY Choose. Dog guard?

ANNEX 17 ESF-17 ANIMAL/AGRICULTURE EMERGENCY RESPONSE

Drive More Efficient Clinical Action by Streamlining the Interpretation of Test Results

REPORT ON THE ANTIMICROBIAL RESISTANCE (AMR) SUMMIT

Better Training for Safer Food

FUNDAMENTAL PRINCIPLES OF THE QUALITY OF VETERINARY SERVICES

Dr Mária Szabó Science and NewTechnologies Departement OIE AMR Strategy and the Prudent Use of Antimicrobials

The Veterinary Epidemiology and Risk Analysis Unit (VERAU)

Written Testimony of. Lisa Dolly, Chief Executive Officer, Pershing. on behalf of the. Securities Industry and Financial Markets Association

JEFFERSON COLLEGE COURSE SYLLABUS VAT113 PRINCIPLES OF CLINICAL MEDICINE I. 4 Credit Hours. Prepared by: Dana Nevois, MBA, BS, RVT

GAPFA Update. Diane Loiselle, GAPFA President PFAC Fall Conference 2017

PERSPECTIVES FOR CIRCULAR ECONOMY IN ALENTEJO

RESPONSIBLE ANTIMICROBIAL USE

Effective Vaccine Management (EVM) Global Data Analysis

Responsible Antimicrobial Use

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

The Corporation of Delta COMMISSION REPORT Regular Meeting

Initiatives for Addressing Antimicrobial Resistance in the Environment. Executive Summary

Proposal for a Regulation on veterinary medicinal products

Course # Course Name Credits

of Conferences of OIE Regional Commissions organised since 1 June 2013 endorsed by the Assembly of the OIE on 29 May 2014

TOUCH IOT WITH SAP LEONARDO PROTOTYPE CHALLENGE

Moore County Animal Response Plan. Partner Agency Briefing

OIE PVS Pathway including Veterinary Education

Work of Regional Representations supporting the implementation of the OIE standards on animal welfare

The Economic Impacts of the U.S. Pet Industry (2015)

Transcription:

EVM in Practice Strategic Control throughout Project Life Cycle Peerapong Aramvareekul, Ph.D., PMP, PSP, EVP Ronnie D. Stephens

Peerapong Aramvareekul, Ph.D., PMP, PSP, EVP Born: in Bangkok, Thailand Education: Civil Engineering, Management & Economics Massachusetts Institute of Technology (MIT Sloan) State University of New York at Buffalo (SUNY) Chulalongkorn University Ph.D., M.Eng., MBA, M.A., B.Eng. Work Experience: 15+ years of Construction & Project Management Infrastructure & Construction Engineering & Design Real Estate Development Oil & Gas Currently working: Williams Company, USA Engineer Staff; Project Excellence PLC/PM Hobbies: Spending time with my son, Tennis, Soccer, Reading, Movies Email: Peerapong.Aramvareekul@Williams.com LinkedIn # Tennis & EVM Rock

Ronnie D. Stephens Born: in Tulsa, OK Education: Engineering and Business Chemical Engineering BS Oklahoma State University MBA Pittsburg State University Work Experience: 20+ years of Construction & Project Management Process Engineering/Process Safety Management Chemical processing, manufacturing, and Oil & Gas Executed construction projects in Australia, France, Mexico, South Africa, China, and the United States Currently working: Williams Company, USA Director of Project Life Cycle (PLC) and Project Management Processes Hobbies: Kids, Soccer, Music, Fishing, and Movies Something You Don t Know About Me Once interned as a radio station DJ Email: Ronnie.Stephens@williams.com LinkedIn # Soccer & EVM Rock

Discussion Points Purposes of EVM Causes of Failure when implementing EVM EVM Fundamentals and In Practices EVM Process and Structures Integrated EVM with Stage Gate Model

INTRODUCTION & FUNDAMENTALS FOR THE EVM PROCESS What is EVM? What is EVM used for? Can EVM fail?... If yes, then WHY?

Introduction Earned Value Management (EVM) - a project management technique for measuring project performance and progress in an objective manner. EVM has the ability to combine measurements of scope, schedule, and cost in a single integrated system.. EVM integrates: Scope Time Cost

Introduction EVM integrates: All are interdependent If there is change in one element, at least one of the other two will be changed (or both will be changed) Ability to trade off between Time & Cost

Introduction EVM Benefits Common performance measurement system Data which is timely, valid, and justifiable Data which can be used as a basis for management decisions Cost and schedule performance measurement Isolation of problem areas COMMUNICATION Early identification of problems TOOL Provides an indication of work progress Consistent management reporting on all projects Practical level of metrics and reporting

EVM Fundamentals EVM - Cause Mapping

EVM Fundamentals What are the 3 things needed in order to calculate EVM?

EVM Fundamentals EVM Definitions and Terminology Budgeted Cost of Work Scheduled (BCWS) also called Planned Value (PV): Budgeted resources or dollars representing what is planned to be done by the milestone date (schedule baseline). Budgeted Cost of Work Performed (BCWP) also called Earned Value (EV) : Earned dollars representing what was done based on monthly status updates and rules of progress. (EV = BAC x Physical % Complete) Actual Cost of Work Performed (ACWP) also called Actual Costs (AC), represents what costs where incurred, including accruals, during the reporting period.

EVM Fundamentals Actual Costs versus Earned Value Tracking Actual Costs Actual Costs Earned Value Reporting Earned Value Report $'s spend plan actuals Same Project Same Status $'s spend plan actuals work completion or earned value Time Time Today Today The project is under running planned costs and most of the work is complete Different Conclusion This project is overrunning costs and is significantly behind schedule

EVM Fundamentals Earned Value Management (EVM) $4,000 $3,500 Estimate at Completion (EAC) Cost Overrun $3,000 Cost Variance Value ($) $2,500 $2,000 Schedule Variance Project Budget $1,500 $1,000 $500 $0 BCWS BCWP ACWP Project Slippage 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Status Date BCWS ($) A CWP ($) BCWP ($) Time (Week)

EVM In Practice EVM foundation EVM application Data integration & meaningful information Quality & Value Process Integration

EVM In Practice Three foundations required for an effective EVM WBS that allows actual costs or resources to be tracked at the same level of detail as they were planned. Project Schedule that illustrates how the project will be executed, typically resource loaded. Detailed Estimate which aligned to the project execution plan and schedule.

EVM In Practice Important!!! a. The quality of EVM depends on the quality of project schedule and cost estimate. So, the schedule and cost estimate must reflect how the project will actually be executed. b. SPI from cost based EVM always equal 1.00 when the project is complete no matter whether the project is finished on time or behind schedule. c. Running EVM on early curve and/or on late curve. What should be considered? d. Understanding your actual cost to be used in the EVM calculations.

EVM In Practice EVM: Cost-Based vs Time-Based

EVM In Practice EVM: on Early and Late Curves

EVM In Practice Actual Cost of Work Performed (ACWP) Total costs incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work package ACWP EAC Actual Cost of Work Performed Processed Costs Accruals Forecast Actuals (incurred) Estimate to Complete (ETC) 11/12/12 4/30/13 10/31/15

EVM In Practice Stakeholder Engagement & Communication Types of EVM Stakeholders Process Champions Step 1.: Identify the stakeholders Data Providers Analyst or Project Controls End Users Step 4.: Establish engagement & communication method EVM Stakeholder Analysis Step 3.: Create a relationship model Step 2.: Profile the stakeholders Unengaged sponsor sinks the ship. Angela Waner

EVM In Practice Key take away points EVM is not just a Plug & Play methodology. In order for an EVM system to be effective, it must integrate with your companies other Processes

Plan Organize Authorize EVM In Practice Collect Calculate The Process & Cycle of EVM Status Interpret Translate Report Corrective Action

EVM In Practice Time Spending Collect / Measure Calculate / Statusing Interpret / Analyze Translate to Solutions Communicate Planned Value (PV) Actual Cost (AC) Earned Value (EV) Schedule Cost Schedule Variance (SV) Schedule Performance Index (SPI) Estimate at Completion (EACt) Estimate to Complete (ETCt) Cost Variance (CV) Cost Performance Index (CPI) Estimate at Completion (EACc) Estimate to Complete (ETCc) > 1 is ahead schedule = 1 is on schedule < 1 is behind schedule various scenarios > 1 is budget underrun = 1 is on budget < 1 is budget overrun various scenarios Report Decision & Corrective Action

EVM In Practice Typical Project Controls Practitioners Spend 61% of Their Time on Unproductive Activities Source: studied by EcoSys customer

EVM In Practice Best in class Project Controls Targeted Utilization Source: studied by EcoSys customer

EVM Foundations & Structures PEOPLE PLANNING GG PROCESS TOOLS

Tools / Techniques Interpretation Certainty Predictability Repeatability People / Culture Process / Procedure EVM Foundations & Structures Corrective Action Communication Detailed Estimate Project Schedule Work Breakdown Structure (WBS)

EVM & Stage Gate Implementation

EVM & Stage Gate Implementation Integrated EVM throughout E&C Stage Gate Process Decide to Initiate Decide to Proceed Decide to Continue Decide to Sanction Operations Handoff Close Out Does the opportunity support economic development? Is the project technically & commercially viable? Optimize the recommended technical and economical concept Do the budget, timeline, and commercial terms support full sanction? Is the asset ready for operation? EVM executed Have the lessons learned been captured? Is the asset performing as expected?

EVM & Stage Gate Implementation Integrated EVM throughout E&C Stage Gate Process

EVM & Stage Gate Implementation Integrated EVM throughout E&C Stage Gate Process WBS, Created/Customized to fit the project

EVM & Stage Gate Implementation Work Breakdown Structure (WBS) Permitting/ Environment Civil Electrical Conduit & Materials Chartering Engineering Long Lead Electrical, Valves, Pipes, Site Instrumentation work & Fittings & Controls Procurement Construction Commissioning Closeout Land/ROW Compressor Procurement Power Structural Steel Management, process, and organization Planning, scheduling, and budgeting Data, tracking, and communication Analysis and management reporting Maintenance, revisions, and lessons learned

EVM & Stage Gate Implementation Permitting/ Environment Civil Electrical Conduit & Materials Work Breakdown Structure (WBS) Chartering Land/ROW Engineering Long Lead Electrical, Valves, Pipes, Site Instrumentation work & Fittings & Controls Procurement Compressor Procurement Power Power Compressor RFQ Structural Steel Compressor Construction Commissioning Closeout Issue Compressor RFQ Submit Compressor PO Receive Compressor Specs from Vendor 1 st Payment 25% for Compressor 2 nd Payment 25% for Compressor 3 rd Payment 25% for Compressor Management, process, and organization Planning, scheduling, and budgeting Final Payment 25% for Compressor Receive Compressor Data, tracking, and communication Analysis and management reporting Maintenance, revisions, and lessons learned

EVM & Stage Gate Implementation Work Breakdown Structure (WBS) Permitting/ Environment Civil Electrical Conduit & Materials Chartering Issue Compressor RFQ Engineering Submit Compressor Compressor Land/ROW Land/ROW PO Procurement Receive Compressor Specs from Vendor 1 st Payment 25% for Compressor 2 nd Payment 25% for Compressor 3 rd Payment 25% for Compressor Long Lead Electrical, Valves, Pipes, Site Instrumentation work & Fittings & Controls Procurement Power Final Commercial/Business Payment 25% for Compressor Development Receive Compressor Project Management/Compliance/Regulatory Analysis and management reporting Compressor RFQ FS+10d SS Structural FS+20d Steel FS+30d Compressor Construction FS+6mon FS+40d Commissioning FS+40d Closeout Maintenance, revisions, and lessons learned

EVM & Stage Gate Implementation

EVM Summary Summary!!! a. EVM is a project management technique that integrates Scope, Schedule, and Cost. b. To calculate EVM, the three inputs needed are Planned value, Earned value, Actual cost c. Critical EVM foundations are WBS, Project Schedule, and Detailed Estimate that integrated with project schedule. d. To set up an effective EVM process, it must be integrated throughout a companies project stage gate. It is a. PROCESS. e. EVM In Practice for better value and quality integrates EVM Foundation, Stakeholder Engagement & Communication, and Process Integration. f. EVM should be used as a COMMUNICATION tool. Data is like garbage. You d better know what you are going to do with it before you collect it. Mark Twain

EVM Summary EVM Process Map for E&C projects Plan & Organize Collect & Review Calculate & Status Analyze & Interpret Translate to Solutions Communicate & Report Corrective Action Contracting SOV Planning: Budget & Scheduling Justifiable Project Control Construction Construction Schedule EVM Tracking Forms EVM Reports Tracking Reporting Lessons Learned EVM Construction ($$$ or MHW) Be Proactive Decision Making Manage by Exception Certainty Predictability Repeatability Business Opportunities Improvement Opportunities Contractor Performance Database

EVM Summary EVM In-Practice Data integration & meaningful information Quality & Value Process Integration