Using Earned Value in Scientific Research. David Roberts & Sheila Roberts CUPE International.
|
|
- Mavis Carr
- 5 years ago
- Views:
Transcription
1 Using Earned Value in Scientific Research David Roberts & Sheila Roberts CUPE International.
2 Discussion of EVM in Scientific Research Exploring a behavioural approach to adopting EVM. Challenges Mindset Scientific work and mindset Earned Value Management work and mindset Culture Can Science & Management cultures work with EVM? What Outcomes and Benefits would be mutually attractive to Science & Management? Implementation Approach Evidence Is there compelling evidence for the use of EVM? What are the options for change to using EVM? Collaboration What we did: working together to design EVM Light What others said in response: Stakeholder Quotes/Perspectives Learning Agility & Engagement Summary of our working approach. Learning EVM Evolution: Tailoring around the Teams: so far-so good. 2
3 The Challenge: Can the value of Scientific Research be improved using EVM? An international scientific programme; is seeking to drive greater value from current vaccine stockpiles future Global Pandemic It is a challenging test environment for EVM providing PM insight in the years ahead. 3
4 Scientific Concerns & Methods Can vaccine stockpiles prevent the next Pandemic? Pandemicpandemic? In global health, emergency vaccine stockpiles are like the insurance policy you never really wanted to take out; you resent the cost and have mixed feelings about never making a claim. Ideally, you never have to use it. 4
5 Global trends in Urbanisation (UN 2015) The worst-case scenario is an outbreak in huge cities, such as Mumbai, Beijing or Lagos, where even diseases that are relatively difficult to transmit, like Ebola, could prove difficult to contain. Such so-called mega-cities are a growing trend. 5
6 Scientific Research & Work Flow Review Existing Stockpiles Scientific Work Research Next Mutations Research Vaccine Scalability Improved Insurance Policy 6
7 Scientific Mindset Scientific Information takes the form of research findings and statistical data Work packages comprise Project planning, laboratory testing and mathematical modelling. Visualisation of this work can be expressed using Antigenic Maps. 7
8 Scientific Paradigm 8
9 Value Management Principles 9
10 EVM Earning Value Better Performance What and why? Traditional Planned Value: PMB Baseline: Task driven plans; Fixed scope, schedule, costs Focus Forwards Cost & Schedule Variance Agile Planned Value: PRL Baseline: Fixed time & costs; Multiple sprint plans, changes, delivery Focus Forwards Functionality & Features Variance Estimate to Completion or Estimate at Completion 10
11 Earned Value Management Mindset Management Information takes the form of Plans, Budgets, Accounting Systems, and Control Reports. Findings and statistical data provide Forecasts and Lessons. 11
12 EVM Paradigm Normal Earned Value Management Planned value is at the heart of project work; EVM focusses on cost/schedule estimates, variations and forecasts to agreed budgets, using measurements, ratios and indices. Improved EVM performance requires changes to planned project processes and/or practices, innovation & smarter ways of working, leading to better project outcomes & higher project-team/stakeholder satisfaction. Inspires PMs to deliver stakeholder goals 12
13 Common & Contrasting Cultures Science Activities in common: Measurement Data Analysis Statistics Lessons Attitudes can be different: Team or self focus Attract resources Freedom in decisions Puzzles or Discovery Management Activities in Common: Measurement Data Analysis Statistics Lessons Attitudes can be different: Organisational focus Return on resources Decisions to control Accountability Activities quite similar but attitudes quite dissimilar 13
14 Blending Science & Management Methods Can Earned Value Management work in Science? Science and management are seen as polar opposites; management simply gets in the way of good science! Little understood evidence that PM or VM works (Gartner et al), despite 100 years of scientific management. 14
15 Does EVM Work? GAO Cost Estimating & Assessment Guide:- -17 Best Practices checklist for cost estimates 48 case studies; 9 graded levels of technology Project personnel should use the GOA guide as applicable to Office of Science Projects. 15
16 Does EVM Work? Journal of Cost Analysis and Parametrics:- - According to David Christensen and Kirk Payne, in research conducted by the U.S. Air Force in the early 1990s: A project's cumulative CPI at 20% project completion, doesn't change by more than 10% for remaining project. If a project is underperforming financially at 20% project completion, it won't improve unless significant corrective measures are taken. 16
17 Paradigm Shift or Evolution Can Earned Value Management really bring about a transformation in science? 17
18 Paradigm Shift or Evolution? Can Earned Value Management really bring about a transformation in science? 18
19 Nudge Theory would suggest EVM Light EVM is now mandated for publically-funded projects in USA; An implementation standard ANSI 748;and APM Compass: Software Tools too; Tailoring EVM to fit Scientific Research Culture and Projects. 19
20 Part Two: What should EVM Light look like - Implementation and Learning. 20
21 Stakeholder Interests (1-4) 1.Scientists 2.Universities Discovering Enabling & Solving Capability EVM De-Risking & Delivering 3. Research Institute 4. Government - Demonstrating Value 21
22 Stakeholder Value is Key to EVM 22
23 Stakeholder Value Drivers Scientists: Puzzle Solving & Discovering - As a researcher I want to explore what is unknown and publish discoveries Universities: Enabling Capability - As a University I want to build an International reputation for high quality research Research Institute: De-Risking & Delivering As an Institute I want to commission and implement the outcomes of scientific research Government: Demonstrating Value As a Government Department I want VFM from taxes 23
24 Magic Recipe EVM Light Ingredients Outcomes EVMS Expertise Behavioural EVM Plan Timely Reports Healthy Debate Better decisions 24
25 PROJECT BOARD EVMS DECISION MAKING Approvals Plans Controls Updates Changes Risk Oversight Current Performance Forecast to Completion Reliability EVMS & Integrity Compliance Outcomes Reports and Forecasts CONTRACT Scope CHANGES ANALYSIS & CONTROL LESSONS PROJECT Agreed Contract with SoW Appoint PM & Scientific Teams Control A/C Mgmt Risk Register Create Create OBS OBS EVMS ENGINE Project Plan WBS WP PP RAM (CAs & CAMs) EVTs Create Project Schedule Confirm Milestones Allocate budgets to CA/WPs Cost/Schedule Risk Analysis Establish PMB PROJECT CONTROL Update cost schedule Baseline Maintenance Risk Management Issues & Changes PROJECT ANALYSIS PMB Variances C/ SPI Cost Performance s CLIENT :PROJECT PERFORMANCE Reporting m/q Reports annual Forecasts /EAC CHANGE REQUEST Authorised change Re-Plan/Prg. Re-Baseline Update EVMS FINANCIAL SYSTEM Planned Value (BCWS) Budget Allocation Distributed Budget Funding Payments FORECASTING In year outcomes EAC + TCPI CV + SV +VAC Planning assumptions RESEARCH FUNDS 25
26 EVM Implementation Agile or Traditional Project Environments. Assess EVM Maturity - 5 Level Model (APM Compass) Establish Expectations for Project Reporting & Control Verify/Confirm Current EVM Practices (e.g. Plans, Budgets, Control Accounts/ Control Account Managers) Clarify how the EVM gap is to be filled.(training or Outsourced Services) Validate Customer/Supplier satisfaction with new practice Identify Lessons and implement them in Planning. 26
27 Solution Outcome Solutions and Outcomes Allow Scientific Research to flourish Allocate techniques based on science Use sprints / prioritized plans Use scientific progress data Update plan when outcomes are known Identified CPR 1 and 5 only Research progresses Plans are current EVM raises important discussion points Collaboration between scientists & managers 27
28 Solution Solutions and Benefits Allow Scientific Research Enable high quality reputation De-risk delivery of outcomes Confirm value from public spending Benefits Objective Progress measurement techniques Project is continually aligned to objectives Securing funding into the future Confidence in collaboration 28
29 Learning 29
30 EVM in Complex Environments 30
31 Collaborate to Overcome Blockers Government Department Research Institute University Historical Beliefs: Scientists Minimise Management restricts scientific / academic freedom Maximise Research Quality power + prestige + income Comlpy with Governance pre-requisite for future spending Overcome Too cumbersome - too costly without proven benefits? 31
32 Findings to date: What the Project Managers Say EVM enabled us to show our funders that we, as an academic led-consortium, can manage large multimillion dollar budgets carefully and provide excellent value in our work EVM helps us to more easily identify any areas where spending may have varied against what we forecast and to re-plan accordingly Getting research staff to understand the uses of EVM is a challenge - scientists always prefer to be doing science! 32
33 Thank you for sharing your time with us. David and Sheila Roberts CUPE International 2018 Office:
Earned Value Management Practitioners Symposium
Earned Value Management Practitioners Symposium 23 JUL 2015 Backdrop Challenges Overcoming the challenges Q&A 2 Who we support What they do What they buy, manage, and oversee 7/26/2015 3 Established 2006
More informationGAO Earned Value Management (EVM) Audit Findings
GAO Earned Value Management (EVM) Audit Findings Based on Best Practices for EVM in the GAO Cost Estimating and Assessment Guide Karen Richey December 2012 EVM is an Important Management Decision Support
More informationEVM in Practice. Strategic Control throughout Project Life Cycle. Peerapong Aramvareekul, Ph.D., PMP, PSP, EVP Ronnie D. Stephens
EVM in Practice Strategic Control throughout Project Life Cycle Peerapong Aramvareekul, Ph.D., PMP, PSP, EVP Ronnie D. Stephens Peerapong Aramvareekul, Ph.D., PMP, PSP, EVP Born: in Bangkok, Thailand Education:
More informationPARCA. DoD EVM Policy Initiatives. Mr. John McGregor PARCA Deputy Director for EVM. NDIA IPMD Meeting August 29, 2018
NDIA IPMD Meeting August 29, 2018 PARCA DoD EVM Policy Initiatives Mr. John McGregor PARCA Deputy Director for EVM 1 PARCA Policy Initiatives Agile and EVM Guide Update Questions 2 Director, Performance
More informationEARNED VALUE MANAGEMENT WHAT IS IT AND WHY SHOULD I CARE?
Slide 1 EARNED VALUE MANAGEMENT WHAT IS IT AND WHY SHOULD I CARE? ROBIN PULVERENTI 2018 Project Management Symposium Slide 2 What is EVM KEY CONCEPTS Slide 3 Is it EV, EVM, or EVMS? Earned Value EV = Budgeted
More informationThe EVM + AGILE Anthology
The EVM + AGILE Anthology Ray W. Stratton, PMP, EVP Management Technologies raystratton@mgmt-technologies.com Project Management Institute California Inland Empire Chapter 17 February 2015 Who is this
More informationApplicability of Earn Value Management in Sri Lankan Construction Projects
Applicability of Earn Value Management in Sri Lankan Construction Projects W.M.T Nimashanie 1 and A.A.D.A.J Perera 2 1 National Water Supply and Drainage Board Regional Support Centre (W-S) Mount Lavinia
More informationDoD EVM POLICY Using EVM and Agile Together
Agile in Govt Summit April 20, 2017 APPROVED FOR PUBLIC RELEASE DISTRIBUTION 1 DoD EVM POLICY Using EVM and Agile Together Mr. John McGregor PARCA Deputy Director for EVM 2 Agenda PARCA EVM and Agile Questions
More informationEarned Value Management ASMC Regional PDI Hanscom AFB
! Earned Value Management ASMC Regional PDI Hanscom AFB Phillip Wojcik AFLCMC EVM Focal November 15, 2017 My Background 2 50 Years Old! Happy Birthday EVM!!! Started in 1967 as Cost/Schedule Control Systems
More informationLessons learned from implementing EVM on a large scale IT portfolio at the Department of State
Lessons learned from implementing EVM on a large scale IT portfolio at the Department of State D a n n y Toler, Director E n t e r p r i s e N e t w o r k Management ( I R M / O P S / E N M ) U n i t e
More informationEVM for the Rest of Us
Project Controls Expo 13 th Nov 2013 Twickenham Stadium, London EVM for the Rest of Us About the Speaker Javier Sloninsky o o o o CEO of EcoSys - powerful, easy- to- use enterprise project controls sonware
More informationCreating Strategic Capital for EVM. EVA th June 2012 Andrew Hill PROJECT CONTROLS CONSULTING
Creating Strategic Capital for EVM Responsible for the successful delivery of projects for our clients EVA 17 13 th June 2012 Andrew Hill Strategic Capital What is strategy? Analytical thinking & commitment
More informationNational Action Plan development support tools
National Action Plan development support tools Sample Checklist This checklist was developed to be used by multidisciplinary teams in countries to assist with the development of their national action plan
More informationAdvanced Uses of Earned Value Management in Projects, Programmes and Portfolios
Advanced Uses of Earned Value Management in Projects, Programmes and Portfolios A Practical Approach based on Real-Life Experiences Alexandre Rodrigues, CEng. Prof. Ph.D. PMP PMO Projects UK PMO Projects
More informationSociology of Dogs. Learning the Lesson
Sociology of Dogs Learning the Lesson When we talk about how a dog can fit smoothly into human society, the key to success is how it can adapt to its environment on a daily basis to meet expectations in
More informationAerial view of the Faculty of Veterinary Medicine Utrecht
Aerial view of the Faculty of Veterinary Medicine Utrecht The role of a veterinarian in the next 30 years Anton Pijpers Utrecht University Content What s happening around us In general Societal demands
More informationEXTENSION PROGRAMMES
EXTENSION PROGRAMMES DEDICATED TO THE ACTIVITIES OF THE VETERINARY SERVICES G. Khoury International Consultant 1 Original: English Summary: Extension programmes could be defined as the dissemination of
More informationBuilding Responsible Pet Ownership Communities The Calgary Model. Thursday, October 22, 15
Building Responsible Pet Ownership Communities The Calgary Model In North America we do not have a problem with pet overpopulation, stray animals, nuisance or vicious animals we have a problem with responsible
More informationApplication of EVM to Contracts
Note: This document is for reference only and not all inclusive of information contained in source references Basic Earned Value Management (EVM) Requirements EVM Applicability EVM applies to cost or incentive
More informationMEASUREMENT WHO NEEDS IT?!! Walt Lipke PMI - Oklahoma City
Europe EVM 2013 Copyright Lipke 2013 1 MEASUREMENT WHO NEEDS IT?!! Walt Lipke PMI - Oklahoma City +1 405 364 1594 waltlipke@cox.net www.earnedschedule.com Copyright LipkeEurope 2013 EVM 2013 2 Abstract
More informationEffective Vaccine Management Initiative
Effective Vaccine Management Initiative Background Version v1.7 Sep.2010 Effective Vaccine Management Initiative EVM setting a standard for the vaccine supply chain Contents 1. Background...3 2. VMA and
More informationEVM Practice & Future Trend
A Global and Cross-Industry Perspective on EVM Practice & Future Trend Lingguang Song, Ph.D Construction Management University of Houston Outline 1. Introduction Motivation & objectives Methodology & definitions
More informationDr Marc Sprenger Director Antimicrobial Resistance Secretariat Global action plan on antimicrobial resistance
Global Action Plan on Antimicrobial Resistance Dr Marc Sprenger Director Antimicrobial Resistance Secretariat When are we entering the post-antibiotic era? For some diseases we have already entered! Fatal
More informationClick to edit Master title style
Click to edit Master title style 0 Click Surviving to edit Today s Master title style Earned Value Management System (EVMS) Environment Breakout Session #G12 Dale Gillam, MBA, CPCM, PMI-SP, CSSGB, CSM,
More informationPosition Description PD895 v3.1
Puppy Development Team Leader Position Level Team Leader Department GDS Location South Australia Direct/Indirect Reports Casual Breeding Centre Attendants Puppy Development Centre Volunteers Direct Reports
More informationfunded by Reducing antibiotics in pig farming
funded by Reducing antibiotics in pig farming The widespread use of antibiotics (also known as antibacterials) in human and animal medicine increases the level of resistant bacteria. This makes it more
More informationStrategy 2020 Final Report March 2017
Strategy 2020 Final Report March 2017 THE COLLEGE OF VETERINARIANS OF ONTARIO Introduction This document outlines the current strategic platform of the College of Veterinarians of Ontario for the period
More informationDevelopment and improvement of diagnostics to improve use of antibiotics and alternatives to antibiotics
Priority Topic B Diagnostics Development and improvement of diagnostics to improve use of antibiotics and alternatives to antibiotics The overarching goal of this priority topic is to stimulate the design,
More informationGOOD GOVERNANCE OF VETERINARY SERVICES AND THE OIE PVS PATHWAY
GOOD GOVERNANCE OF VETERINARY SERVICES AND THE OIE PVS PATHWAY Regional Information Seminar for Recently Appointed OIE Delegates 18 20 February 2014, Brussels, Belgium Dr Mara Gonzalez 1 OIE Regional Activities
More informationOIE Strategy for Veterinary Products and Terms of Reference for the OIE National Focal Points
OIE Strategy for Veterinary Products and Terms of Reference for the OIE National Focal Points Dr Elisabeth Erlacher-Vindel, Deputy Head of the Scientific and Technical Department OIE Strategy for Veterinary
More informationFrom the CEVM. Department of the Navy (DON) Earned Value Management (EVM) Quarterly Newsletter. October Inside this issue:
Welcome to the first anniversary edition of The Baseline. We will continue this effort as long as there are loyal readers and informative content. If you are interested in contributing to this publication,
More informationResolution adopted by the General Assembly on 5 October [without reference to a Main Committee (A/71/L.2)]
United Nations A/RES/71/3 General Assembly Distr.: General 19 October 2016 Seventy-first session Agenda item 127 Resolution adopted by the General Assembly on 5 October 2016 [without reference to a Main
More informationIntroduction Methods to Track Changes in Cobra Cobra Project Preferences Cobra New Feature Change Log Summary
Keith Anderson, PMP Implementation Practice Lead, PrimePM EVM Practitioners Forum, July 2014 Introduction Methods to Track Changes in Cobra Cobra Project Preferences Cobra 5.1.2 New Feature Change Log
More informationStray Dog Population Control
Stray Dog Population Control Terrestrial Animal Health Code Chapter 7.7. Tikiri Wijayathilaka, Regional Project Coordinator OIE RRAP, Tokyo, Japan AWFP Training, August 27, 2013, Seoul, RO Korea Presentation
More informationof Conferences of OIE Regional Commissions organised since 1 June 2013 endorsed by the Assembly of the OIE on 29 May 2014
of Conferences of OIE Regional Commissions organised since 1 June 2013 endorsed by the Assembly of the OIE on 29 May 2014 2 12 th Conference of the OIE Regional Commission for the Middle East Amman (Jordan),
More informationOutcomes of AVSBN 2017
Outcomes of AVSBN 2017 Prof. Dr. Achariya Sailasuta, Vice President of Veterinary Council of Thailand, VCT Department of Pathology, Faculty of Veterinary Science, Chulalongkorn University Bangkok, Thailand
More informationRobert Bob Rovinsky 2018 Project Management Symposium
Slide 1 A CASE STUDY IN USING EVM TO IMPROVE PROJECT MANAGEMENT AND GAIN FUNDING: THE FEDERAL AVIATION ADMINISTRATION (FAA) STORY Robert Bob Rovinsky 2018 Project Management Symposium Slide 2 Contents
More informationinternational news RECOMMENDATIONS
The Third OIE Global Conference on Veterinary Education and the Role of the Veterinary Statutory Body was held in Foz do Iguaçu (Brazil) from 4 to 6 December 2013. The Conference addressed the need for
More informationMSc in Veterinary Education
MSc in Veterinary Education The LIVE Centre is a globally unique powerhouse for research and development in veterinary education. As its name suggests, its vision is a fundamental transformation of the
More informationFUNDAMENTAL PRINCIPLES OF THE QUALITY OF VETERINARY SERVICES
FUNDAMENTAL PRINCIPLES OF THE QUALITY OF VETERINARY SERVICES DEVELOPMENT OF PUBLIC-PRIVATE PARTNERSHIPS TO SUPPORT VETERINARY SERVICES Rabat, Morocco, 16 February 2015 Gideon Brückner President OIE Scientific
More informationWHO (HQ/MZCP) Intercountry EXPERT WORKSHOP ON DOG AND WILDLIFE RABIES CONTROL IN JORDAN AND THE MIDDLE EAST. 23/25 June, 2008, Amman, Jordan
WHO (HQ/MZCP) Intercountry EXPERT WORKSHOP ON DOG AND WILDLIFE RABIES CONTROL IN JORDAN AND THE MIDDLE EAST 23/25 June, 2008, Amman, Jordan Good practices in intersectoral rabies prevention and control
More informationOverview of the OIE PVS Pathway
Overview of the OIE PVS Pathway Regional Seminar for OIE National Focal Points for Animal Production Food Safety Hanoi, Vietnam, 24-26 June 2014 Dr Agnes Poirier OIE Sub-Regional Representation for South-East
More informationDoD EVM. EVM Requirements, Application, Reporting, & Execution. Mr. John McGregor PARCA Director for EVM. David Nelson Karen Kostelnik
1 DAU Acquisition Training Symposium 04-04-17 DoD EVM EVM Requirements, Application, Reporting, & Execution Mr. John McGregor PARCA Director for EVM David Nelson Karen Kostelnik A Few Words APPROVED FOR
More informationCombating Antibiotic Resistance: New Drugs 4 Bad Bugs (ND4BB) Subtopic 1C. Seamus O Brien and Hasan Jafri Astra Zeneca and MedImmune
Combating Antibiotic Resistance: New Drugs 4 Bad Bugs (ND4BB) Subtopic 1C Seamus O Brien and Hasan Jafri Astra Zeneca and MedImmune Need for public-private collaboration Challenges of AB R&D: 1. Unique
More informationDog Population Management Veterinary Oversight. Presented by Emily Mudoga & Nick D'Souza
Dog Population Management Veterinary Oversight Presented by Emily Mudoga & Nick D'Souza DOGS IN COMMUNITIES In communities dogs provide benefits:- Companionship, Security; Herding; Specialized aid e.g.
More informationInvesting in Human Resources in Veterinary Services
Investing in Human Resources in Veterinary Services 9 th Conference of Ministers responsible for Animal Resources in Africa Meeting of Experts Abidjan, Côte d Ivoire, 16-17 April 2013 Dr. Etienne Bonbon
More informationOIE standards on the Quality of Veterinary Services
OIE standards on the Quality of Veterinary Services OIE regional seminar on the role of veterinary paraprofessionals in Africa Pretoria (South Africa), October 13-15, 2015 Dr. Monique Eloit OIE Deputy
More informationCommittee for Medicinal Products for Veterinary Use (CVMP) Work Plan 2018
7 December 2017 Committee for Medicinal Products for Veterinary Use (CVMP) Committee for Medicinal Products for Veterinary Use (CVMP) Work Plan 2018 Chairpersons Chair: D. Murphy Status Adopted in December
More informationBuilding Competence and Confidence. The OIE PVS Pathway
Dr. Alain Dehove (OIE) Coordinator of the World Animal Health and Welfare Fund Building Competence and Confidence The OIE PVS Pathway OIE Global Conference on Wildlife Animal Health and Biodiversity -
More informationFrom Bid Package to Detailed EVM Baseline in One Easy Step, Can it be Done?
From Bid Package to Detailed EVM Baseline in One Easy Step, Can it be Done? Karen Stiff Naval Air Warfare Center, Weapons Division China Lake, CA karen.stiff@navy.mil What is a Bid Package? The Cost Breakdown
More informationANTIMICROBIAL RESISTANCE THE AUSTRALIAN CONTEXT. Professor Brendan Murphy Australian Government Chief Medical Officer
ANTIMICROBIAL RESISTANCE THE AUSTRALIAN CONTEXT Professor Brendan Murphy Australian Government Chief Medical Officer AMR in Australia Good understanding but to date not much outcome from actions. The AURA
More informationOIE STANDARDS ON VETERINARY SERVICES ( ), COMMUNICATION (3.3), & LEGISLATION (3.4)
OIE STANDARDS ON VETERINARY SERVICES (3.1-3.2), COMMUNICATION (3.3), & LEGISLATION (3.4) Ronello Abila Sub-Regional Representative for South-East Asia 1 2 CHAPTER 3.1 VETERINARY SERVICES The Veterinary
More informationFOR ANIMALS FOR HEALTH FOR YOU
FOR ANIMALS FOR HEALTH FOR YOU WORLD LEADER IN ANIMAL HEALTH At Zoetis, we discover, develop, manufacture and market veterinary medicines, vaccines and diagnostics, complemented by genetic tests, biodevices
More informationMember Needs Assessment Report to the Members June 2012
Member Needs Assessment Report to the Members June 2012 Background In November of 2011, AVMA completed a comprehensive study among its members to assess how well AVMA s strategic direction aligned with
More informationSpayJax: Government-Funded Support for Spay/Neuter
SpayJax: Government-Funded Support for Spay/Neuter Compiled by ASPCA and PetSmart Charities and distributed to the field, September 2007. Visit the ASPCA National Outreach website for animal welfare professionals:.
More informationOne Health Disease Outbreak Training Scenario
One Health Disease Outbreak Training Scenario Association of American Veterinary Medical Colleges Annual Conference March 2014 Alicia Humlicek, DVM, MPH, DACVPM Pima Medical Institute Tracey Lynn, DVM,
More informationEarned Value & Project Management. Bill Simpson Marshall Space Flight Center NASA EVM Primary Center May 15, 2003
Earned Value & Project Management Bill Simpson Marshall Space Flight Center NASA EVM Primary Center May 15, 2003 NASA EVM: We re Moving to Project Management! Major Changes in the Draft EVM NPD Transfers
More informationThe promise of aquaculture and the challenge of antimicrobial use
The promise of aquaculture and the challenge of antimicrobial use This article is published in two parts. Part 1 identifies the promise of aquaculture and the challenge of antimicrobial use (please see
More informationCity of Fremont Animal Services: Effective Pet Licensing Enforcement
City of Fremont Animal Services: Effective Pet Licensing Enforcement Compiled by ASPCA and PetSmart Charities and distributed to the field, September 2007. Visit the ASPCA National Outreach website for
More informationCOMMISSION OF THE EUROPEAN COMMUNITIES
COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 22 December 2005 COM (2005) 0684 REPORT FROM THE COMMISSION TO THE COUNCIL ON THE BASIS OF MEMBER STATES REPORTS ON THE IMPLEMENTATION OF THE COUNCIL RECOMMENDATION
More informationSurveillance. Mariano Ramos Chargé de Mission OIE Programmes Department
Mariano Ramos Chargé de Mission OIE Programmes Department Surveillance Regional Table Top Exercise for Countries of Middle East and North Africa Tunisia; 11 13 July 2017 Agenda Key definitions and criteria
More informationRSPCA SA v Ross and Fitzpatrick Get the Facts
RSPCA SA v Ross and Fitzpatrick Get the Facts RSPCA South Australia is releasing the following questions and answers to address the extensive misinformation being communicated on social media about our
More informationCats Protection our strategy and plans
Cats Protection our strategy and plans Version 6-03.09.15 COM_881 www.cats.org.uk Cats Protection now helps around 500 cats and kittens every day through our network of over 250 volunteer-run branches,
More informationVNA Level III Module 1: Business Realities
VNA Level III Module 1: Business Realities Learning Objectives After completing this module, the benefits you realize should include: Understanding some of the costs of operating a successful veterinary
More informationEconomic Value Management (EVM) 2007 results
Value Management (EVM) 2007 results Analyst and investor conference call Zurich, EVM methodology EVM is Swiss Re s integrated economic measurement and steering framework used for planning, pricing, reserving
More informationDogs and Cats Online All of our Puppies in One Basket
Dogs and Cats Online All of our Puppies in One Basket Now: Many baskets 68 council dog registers. Each has different ways of storing information about Control Orders, and owner Prohibition Orders. 6 SA
More informationContact Person: Dr Samuel Kahariri; Dr Samuel Makumi;
THE KENYA VETERINARY ASSOCIATION Head Office Veterinary Research Labs, Kabete P.O. Box 28089 Kangemi 00625 Nairobi, Telephone: +254 (20) 808 5685, Mobile: +254 (727) 680 022, Email: info@kenyavetassociation.com;
More informationREPORT ON THE ANTIMICROBIAL RESISTANCE (AMR) SUMMIT
1 REPORT ON THE ANTIMICROBIAL RESISTANCE (AMR) SUMMIT The Department of Health organised a summit on Antimicrobial Resistance (AMR) the purpose of which was to bring together all stakeholders involved
More informationPromoting One Health : the international perspective OIE
Promoting One Health : the international perspective OIE Integrating Animal Health & Public Health: Antimicrobial Resistance SADC SPS Training Workshop (Animal Health) 29-31 January 2014 Gaborone, Botwana
More informationAntimicrobial Use and Antimicrobial Resistance a strategy for animal agriculture Forum 2014
Antimicrobial Use and Antimicrobial Resistance a strategy for animal agriculture Forum 2014 Working Group NFAHW Council-Michel Major (chair), Jim Fairles, Jennifer MacTavish, Scott Dingwell, Marc Cormier
More informationGlobal Coordination of Animal Disease Research. Alex Morrow
Global Coordination of Animal Disease Research Alex Morrow Focus of Presentation Background to STAR-IDAZ Activities and outputs/outcomes of STAR-IDAZ Priority topics Long-term research needs Plans for
More informationPan-Canadian Framework and Approach to Antimicrobial Resistance. Presentation to the TATFAR Policy Dialogue September 27, 2017
Pan-Canadian Framework and Approach to Antimicrobial Resistance Presentation to the TATFAR Policy Dialogue September 27, 2017 PURPOSE Purpose To provide TATFAR members with an overview of Canada s coordinated
More informationComments from The Pew Charitable Trusts re: Consultation on a draft global action plan to address antimicrobial resistance September 1, 2014
Comments from The Pew Charitable Trusts re: Consultation on a draft global action plan to address antimicrobial resistance September 1, 2014 The Pew Charitable Trusts is an independent, nonprofit organization
More informationCOMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE COMMANDER SPACE AND MISSILE SYSTEMS CENTER SPACE AND MISSILE SYSTEMS CENTER INSTRUCTION 63-107 4 AUGUST 2010 Certified Current 7 September 2012 Acquisition EARNED VALUE MANAGEMENT (EVM)
More informationSteve Wake Chairman Association for Project Management UK. Slide 1
Steve Wake Chairman Association for Project Management UK Slide 1 The UK MoD EVM operating environment (maybe) Slide 2 Three nations divided by a common language Slide 3 3 2004: USA UK Reciprocity Agreement
More informationWHY STAKEHOLDER ENGAGEMENT IS CRITICAL TO OIE STRAY DOG INITIATIVE
WHY STAKEHOLDER ENGAGEMENT IS CRITICAL TO OIE STRAY DOG INITIATIVE Dogs & People 2016: Mastering Stakeholder Engagement for Sustainable Impacts Dr Mark Schipp OIE Delegate Australia Vice-President of the
More informationPrivate Sector Solutions for Public Health Challenges Promoting handwashing practices across Asia
Private Sector Solutions for Public Health Challenges Promoting handwashing practices across Asia Executive Summary Hong Kong & Ho Chi Minh City, Vietnam April 2016 Introduction The Global Institute For
More informationDr Elisabeth Erlacher Vindel Head of Science and New Technologies Departement OIE AMR strategy and activities related to animal health
Dr Elisabeth Erlacher Vindel Head of Science and New Technologies Departement OIE AMR strategy and activities related to animal health Regional Workshop for National Focal Points for Veterinary Products
More informationLitter Education Theme 1: Defining
Litter Education Theme 1: Defining Litter Less Education is comprised of 12 lessons taught over three themes: defining, understanding and actioning. While it is designed to be a complete unit of work,
More informationBenefit Cost Analysis of AWI s Wild Dog Investment
Report to Australian Wool Innovation Benefit Cost Analysis of AWI s Wild Dog Investment Contents BACKGROUND 1 INVESTMENT 1 NATURE OF BENEFITS 2 1 Reduced Losses 2 2 Investment by Other Agencies 3 QUANTIFYING
More informationTntibiotic resistance is a growing problem and the main cause of this problem is misuse
AIHA Internet Resources Digest Supporting Access to High Quality Online Resources June 2015 Spotlight on: Resources on Rational Antibiotic Use Tntibiotic resistance is a growing problem and the main cause
More informationTHE IMPORTANCE OF QUALITY IN COMPOUNDED VETERINARY MEDICINES
THE IMPORTANCE OF QUALITY IN COMPOUNDED VETERINARY MEDICINES GOOD MANUFACTURING PRACTICES On the 12th of June 2015 Bova was the first pharmacy in Australia to be granted a licence to manufacture veterinary
More informationOIE Regional Commission for Europe Regional Work Plan Framework Version adopted during the 85 th OIE General Session (Paris, May 2017)
OIE Regional Commission for Europe Regional Work Plan Framework 2017-2020 Version adopted during the 85 th OIE General Session (Paris, May 2017) Chapter 1 - Regional Directions 1.1. Introduction The slogan
More informationBuilding Rapid Interventions to reduce antimicrobial resistance and overprescribing of antibiotics (BRIT)
Greater Manchester Connected Health City (GM CHC) Building Rapid Interventions to reduce antimicrobial resistance and overprescribing of antibiotics (BRIT) BRIT Dashboard Manual Users: General Practitioners
More informationRegulatory approaches to ensure the safety of pet food
Regulatory approaches to ensure the safety of pet food AVA Submission Submission from the Australian Veterinary Association Ltd 1 20 July 2018 Regulatory approaches to ensure the safety of pet food Introduction
More informationQuestions and Answers on the Community Animal Health Policy
MEMO/07/365 Brussels, 19 September 2007 Questions and Answers on the Community Animal Health Policy 2007-13 Why has the Commission developed a new Community Animal Health Policy (CAHP)? The EU plays a
More informationRecruitment Pack Cattery Team Leader (Part-time) Battersea Dogs & Cats Home
Recruitment Pack Cattery Team Leader (Part-time) Battersea Dogs & Cats Home Dear Applicant, Thank you for requesting further information for our Cattery Team Leader (Part-time) vacancy (Ref BOW323). Please
More informationOIE capacity-building activities
OIE capacity-building activities OIE Regional Seminar for Recently Appointed OIE Delegates Tokyo (Japan) 7-8 February 2012 Dr Mara Gonzalez Ortiz OIE Regional Activities Department OIE Fifth Strategic
More informationApplying PZP Vaccines in the Field:
Applying PZP Vaccines in the Field: An overview of considerations, methods & tools Kali Pereira Senior Wildlife Field Manager The Humane Society of the United States May 2, 2018 Field Application Options
More informationCOPING WITH ANTIMICROBIAL RESISTANCE
JANUARY 2018 COPING WITH ANTIMICROBIAL RESISTANCE REPORT 2 Friends of Europe January 2018 This is truly a global problem that can only be addressed by working together across the planet Tamsin Rose Senior
More informationVice President of Development Denver, CO
Vice President of Development Denver, CO A Nonprofit Community-Based Animal Welfare Organization Committed to Ending Pet Homelessness and Animal Suffering The Dumb Friends League Mission For over 100 years,
More informationIntervention Plan. By: Olivia Bergstrom, Lia Donato, Ashley Hasler, Steve McCollom, and Ashley Staley
Intervention Plan By: Olivia Bergstrom, Lia Donato, Ashley Hasler, Steve McCollom, and Ashley Staley Since our first phone call with Dave Flagler, our group has been focused on the topic of microchipping
More informationKenya SSH4A Results Programme first mid-term review brief
Practice Brief Kenya SSHA Results Programme first mid-term review brief Over the course of one year,5 people in four counties in Kenya gained access to sanitation facilities, 5,07 people began practising
More informationOIE Standards on Animal Welfare, and Capacity Building Tools and Activities to Support their Implementation
OIE Standards on Animal Welfare, and Capacity Building Tools and Activities to Support their Implementation Workshop on animal welfare Organized by EC/TAIEX in co-operation with the RSPCA and State Veterinary
More informationANTIOCH ANIMAL SERVICES
ANTIOCH ANIMAL SERVICES STRATEGIC PLAN July 2009 June 2012 Antioch Animal Services is a bureau of the Antioch Police Department and is responsible for public safety, enforcing local and state laws, as
More informationComponent Specification NFQ Level 5. Sheep Husbandry 5N Component Details. Sheep Husbandry. Level 5. Credit Value 10
Component Specification NFQ Level 5 Sheep Husbandry 5N20385 1. Component Details Title Teideal as Gaeilge Award Type Code Sheep Husbandry Riar Caorach Minor 5N20385 Level 5 Credit Value 10 Purpose Learning
More informationAmerican Veterinary Medical Association
AVMA American Veterinary Medical Association Governmental Relations Division 1910 Sunderland Place, NW Washington, DC 20036-1642 phone 202.789.0007 800.321.1473 fax 202.842.4360 AVMA Headquarters 1931
More informationMarch 18, Richard Avanzino, President Maddie s Fund 2223 Santa Clara Avenue, Suite B Alameda, CA 94501
Richard Avanzino, President Maddie s Fund 2223 Santa Clara Avenue, Suite B Alameda, CA 94501 March 18, 2008 Re: Maddie s Fund Spay/Neuter Application for the Community Collaborative Project in Tuscaloosa
More informationAALAS affiliate BETTER EDUCATION FOR BETTER SCIENCE
AALAS affiliate BETTER EDUCATION FOR BETTER SCIENCE COURSES AND SCIENTIFIC EVENTS 2018 THE FONDAZIONE GUIDO BERNARDINI IN BRIEF never stop learning The Fondazione Guido Bernardini (FGB) is an international
More informationTHE ECONOMIC IMPACT OF THE OSTRICH INDUSTRY IN INDIANA. Dept. of Agricultural Economics. Purdue University
THE ECONOMIC IMPACT OF THE OSTRICH INDUSTRY IN INDIANA by David Broomhall Staff Paper #96-22 September 9, 1996 Dept. of Agricultural Economics Purdue University Purdue University is committed to the policy
More information