Page 1 of 8 NO. 1 - Mobilization / Demobilization: Furnish all labor, materials, tools, equipment, and incidentals necessary for mobilization / demobilization, as specified and shown, for the lump sum price of: NO. 2.1 - Work Sequence No. 1 ( 5 ft. deep trench excavation): Excavate Valve cluster / group #3 Lump Sum 19,894.00 19,894.00 32,000.00 32,000.00 22,000.00 22,000.00 NO. 2.2 - Work Sequence No. 1 ( 5 ft. deep trench excavation): Bracing/Shoring System ( 5 ft. deep trench excavation NO. 2.3 - Work Sequence No. 1 ( 5 ft. deep trench excavation): Investigate condition of Valve #3B Lump Sum 8,783.00 8,783.00 4,100.00 4,100.00 18,000.00 18,000.00 Lump Sum 3,449.00 3,449.00 2,100.00 2,100.00 4,230.00 4,230.00 NO. 2.4 - Work Sequence No. 1 ( 5 ft. deep trench excavation): Repair Valve #3B Extension Rod EA 263.00 263.00 750.00 750.00 6,000.00 6,000.00 EA 1,502.00 1,502.00 550.00 550.00 1,000.00 1,000.00
Page 2 of 8 NO. 2.7a - Work Sequence No. 1 ( 5 ft. deep trench excavation): Furnish 20" BF Valve NO. 2.7b - Work Sequence No. 1 ( 5 ft. deep trench excavation): Replace 20" BF Valve #3A EA 6,046.00 6,046.00 5,700.00 5,700.00 5,618.00 5,618.00 NO. 2.8 - Work Sequence No. 1 ( 5 ft. deep trench excavation): Backfill / Compaction / Pavement Repair EA 11,464.00 11,464.00 6,200.00 6,200.00 6,000.00 6,000.00 NO. 2.9 - Work Sequence No. 1 ( 5 ft. deep trench excavation): Construction Traffic Regulation & Control Lump Sum 9,927.00 9,927.00 6,600.00 6,600.00 15,250.00 15,250.00 NO. 2.1 - Work Sequence No. 1 ( 5 ft. deep trench excavation): Stormwater BMP Checklist Compliance Lump Sum 2,842.00 2,842.00 16,250.00 16,250.00 12,200.00 12,200.00 Lump Sum 971.00 971.00 1,800.00 1,800.00 3,000.00 3,000.00
Page 3 of 8 NO. 3.1 - Work Sequence No. II ( 5 ft. deep trench excavation): Excavate Valve cluster / group #6 NO. 3.2 - Work Sequence No. II ( 5 ft. deep trench excavation): Bracing/Shoring System ( 5 ft. deep trench excavation NO. 3.3a - Work Sequence No. II ( 5 ft. deep trench excavation): Furnish 20" BF Valve Lump Sum 4,692.00 4,692.00 4,100.00 4,100.00 20,000.00 20,000.00 Lump Sum 3,389.00 3,389.00 1,400.00 1,400.00 3,000.00 3,000.00 NO. 3.3b - Work Sequence No. II ( 5 ft. deep trench excavation): Replace 20" BF Valve #6A & #6B EA 6,045.50 12,091.00 5,700.00 11,400.00 5,928.00 11,856.00 NO. 3.4a - Work Sequence No. II ( 5 ft. deep trench excavation): Furnish 12" RSGV EA 8,526.00 17,052.00 5,500.00 11,000.00 6,000.00 12,000.00 EA 4,520.00 4,520.00 4,100.00 4,100.00 4,038.00 4,038.00
Page 4 of 8 NO. 3.4b - Work Sequence No. II ( 5 ft. deep trench excavation): Replace 12" RSGV #6C, and legally dispose of ACP pipe NO. 3.5 - Work Sequence No. II ( 5 ft. deep trench excavation): Backfill / Compaction / Pavement & Landscape Repair EA 6,588.00 6,588.00 7,200.00 7,200.00 5,000.00 5,000.00 NO. 3.6 - Work Sequence No. II ( 5 ft. deep trench excavation): Construction Traffic Regulation & Control Lump Sum 9,037.00 9,037.00 3,100.00 3,100.00 8,500.00 8,500.00 NO. 3.7 - Work Sequence No. II ( 5 ft. deep trench excavation): Stormwater BMP Checklist Compliance Lump Sum 1,778.00 1,778.00 11,600.00 11,600.00 2,500.00 2,500.00 NO. 4.1 - Work Sequence No. III ( 5 ft. deep trench excavation): Excavate Valve cluster / group #14 Lump Sum 971.00 971.00 1,800.00 1,800.00 3,000.00 3,000.00 Lump Sum 5,691.00 5,691.00 7,900.00 7,900.00 10,000.00 10,000.00
Page 5 of 8 NO. 4.2 - Work Sequence No. III ( 5 ft. deep trench excavation): Bracing/Shoring System ( 5 ft. deep trench excavation NO. 4.3a - Work Sequence No. III ( 5 ft. deep trench excavation): Furnish 20" BF Valve Lump Sum 3,671.00 3,671.00 2,200.00 2,200.00 2,000.00 2,000.00 NO. 4.3b - Work Sequence No. III ( 5 ft. deep trench excavation): Replace 20" BF Valve #14A & #14B EA 5,480.50 10,961.00 5,800.00 11,600.00 5,680.00 11,360.00 NO. 4.4a - Work Sequence No. III ( 5 ft. deep trench excavation): Furnish 90 20" SCCP bend, 4" blow-off, fittings EA 8,808.50 17,617.00 4,600.00 9,200.00 5,000.00 10,000.00 NO. 4.4b - Work Sequence No. III ( 5 ft. deep trench excavation): Remove and legally dispose of 20" SCCP fittings, BO's, etc. & replace w/90 20" SCCP bend, 4" BO, fittings, & thrust block. Lump Sum 13,386.00 13,386.00 41,744.00 41,744.00 8,000.00 8,000.00 Lump Sum 2,883.00 2,883.00 38,000.00 38,000.00 18,000.00 18,000.00
Page 6 of 8 NO. 4.5 - Work Sequence No. III ( 5 ft. deep trench excavation): Remove & salvage 20" RSGV #14D NO. 4.6 - Work Sequence No. III ( 5 ft. deep trench excavation): Backfill / Compaction & Pavement Repair EA 1,854.00 1,854.00 1,400.00 1,400.00 3,500.00 3,500.00 NO. 4.7 - Work Sequence No. III ( 5 ft. deep trench excavation): Construction Traffic Regulation & Control Lump Sum 12,209.00 12,209.00 6,000.00 6,000.00 4,000.00 4,000.00 NO. 4.8 - Work Sequence No. III ( 5 ft. deep trench excavation): Stormwater BMP Checklist Compliance Lump Sum 345.00 345.00 900.00 900.00 1.00 1.00 NO. 5.1 - Work Sequence No. IV ( 5 ft. deep trench excavation): Excavate Valve cluster / group #11 Lump Sum 971.00 971.00 1,750.00 1,750.00 2,000.00 2,000.00 Lump Sum 6,797.00 6,797.00 4,100.00 4,100.00 18,000.00 18,000.00
Page 7 of 8 NO. 5.2 - Work Sequence No. IV ( 5 ft. deep trench excavation): Bracing/Shoring System ( 5 ft. deep trench excavation NO. 5.3a - Work Sequence No. IV ( 5 ft. deep trench excavation): Furnish 20" BF Valve Lump Sum 2,824.00 2,824.00 4,000.00 4,000.00 3,000.00 3,000.00 NO. 5.3b - Work Sequence No. IV ( 5 ft. deep trench excavation): Replace 20" BF Valve #11B & #11C EA 5,480.50 10,961.00 5,700.00 11,400.00 5,618.00 11,236.00 NO. 5.4a - Work Sequence No. IV ( 5 ft. deep trench excavation): Furnish 6" Gate Valve EA 8,526.00 17,052.00 5,300.00 10,600.00 8,000.00 16,000.00 NO. 5.4b - Work Sequence No. IV ( 5 ft. deep trench excavation): Replace 6" Gate Valve #11D EA 1,752.00 1,752.00 1,750.00 1,750.00 1,546.00 1,546.00 EA 3,275.00 3,275.00 3,500.00 3,500.00 12,200.00 12,200.00
Page 8 of 8 NO. 5.5 - Work Sequence No. IV ( 5 ft. deep trench excavation): Backfill / Compaction & Pavement Repair NO. 5.6 - Work Sequence No. IV ( 5 ft. deep trench excavation): Construction Traffic Regulation & Control Lump Sum 9,022.00 9,022.00 5,700.00 5,700.00 6,000.00 6,000.00 NO. 5.7 - Work Sequence No. IV ( 5 ft. deep trench excavation): Stormwater BMP Checklist Compliance Lump Sum 2,041.00 2,041.00 11,000.00 11,000.00 4,000.00 4,000.00 NO. 6 - Water Truck Service: Provide Water Truck Service (2000 Gallon Capacity) Lump Sum 971.00 971.00 1,800.00 1,800.00 3,000.00 3,000.00 DAY 1,000.00 10,000.00 750.00 7,500.00 1,000.00 10,000.00 $259,542.00 $313,794.00 $317,035.00 10% Bond 10% Bond 10% Bond