1 Reptile Method Statement Land at the De Winton Hotel Llanbradach Caerphilly Dated September 2015 ON THE INSTRUCTION OF Jon Matthews Of Greenwich Communities Ltd Reported by Richard Watkins 10 Mount Pleasant, Llanelly Hill, Abergavenny, Monmouthshire. NP7 0NT Tel:
2 Method Statement Reptile Mitigation Strategy De Winton Pub, Llanbradach Four native reptile species occur in South Wales, comprising common lizard, slow-worm, adder and grass snake. These four species are all afforded so-called partial protection under the amended Wildlife & Countryside Act 1981, which prohibits the deliberate killing or injury of individuals. However, there is no direct protection extended to the habitats which support these species. All four common reptiles are listed as Priority Species in the UK BAP and its Welsh equivalent The proposed development site includes the detached De Winton Pub and associated gardens including a children s play area, car parking areas, a small area of amenity grassland and hard standing. The proposed development site measures approximately 2797m² and slopes gently from west to east. The De Winton Pub is situated along the eastern boundary of the site adjacent to De Winton Terrace. A small grassed children s play area is located along the northern elevation of the pub building and forms the south east corner of the site boundary. An area of land which previously would have functioned as a garden is present to the south west of the pub. An enclosed car parking are, part tarmacked and part paved, is present to the west (rear) of the pub. A single lane access road leads into the site from the north east of the site along the pub building which leads to a large expanse of tarmac car parking which forms the western site boundary. A small area of grassland is present in the north east corner of the site. Narrow bands of ruderal vegetation line the access road and car parking areas. Two slow worms were found on site during the site inspection, which was undertaken on during July A female slow worm was found under a piece of roofing felt in the garden area. A juvenile slow worm was found under a roofing tile found along the northern boundary in the grassland area to the north east of site. A full reptile survey was not undertaken due to the very small proportion of the site which is suitable for reptiles and the high number of natural refugia present in the suitable reptile habitat. It is felt that the site will only support a small population of reptiles and a full reptile survey would not provide more information. As the whole of the proposed site will be impacted on a translocation scheme for the translocation of reptiles is required. It is proposed to use destructive searching methods in the garden area and the grassland area to the north east of the site. The presence of Japanese Knotweed in the garden area complicates the site clearance methodology. Usually a tracked digger with a toothed bucket would be used to scrape over the top soil and rubble and uncover any reptiles. It is not deemed advisable to use a digger on this site due to concerns over the spread of highly invasive knotweed. Given the small area of potential reptile habitat affected by Japanese knotweed the use of labourers to remove potential suitable reptile habitat by hand is achievable in this instance. It is not proposed to use herptile fencing on site as the small areas of habitat which are suitable for reptiles are isolated from any surrounding habitat by tarmac and buildings. 2
3 Herptile fencing is generally used when a site needs to have reptiles removed from it but to retain habitat within the site which could be suitable for reptiles. As it is proposed to use species deterrence measures once the site has been subject to destructive searching methods the areas will not be suitable for reptiles and they will remain unsuitable until development works are completed. As it is unlikely reptiles will be able to recolonise the site during and post the translocation process it is not proposed to use herptile fencing as part of this strategy. Working Methods A method statement for site clearance will be followed where any reptiles on site will be captured and removed from site to an agreed translocation site. The below species deterrence measures will be followed Site clearance works will be undertaken between April and September inclusive. This will include the removal of suitable features that can be used by reptiles for hibernation. Pointing of suitable gaps in the stone walls found on site. The timing restraints will be implemented to avoid the reptile hibernation period when reptiles could possibly be using refugia such as rubble for hibernation purposes. Care and awareness must be shown when removing any building debris, rubble, brick masonry or timber which is present on site. This will be done under ecological supervision by hand and removed from site immediately. All contractors on site must be made aware of the possibility of endangered species using the site, the legislation protecting them and to show caution during clearance works. Due to the presence of Japanese knotweed on site minimal vegetation disturbance will be used. It is likely some vegetation will be disturbed by the hand removal of suitable reptile habitat from site. However no vegetation will be removed from site. Once the reptile translocation scheme has been completed the site will be chemically sprayed and treated by a suitably experienced Japanese knotweed specialist. The sward must be kept at a maximum height of 50mm to ensure it remains unsuitable for reptiles until the development works are completed. Supervised destructive searching methods will be implemented. Destructive searching methods involve a suitably experienced ecologist being present and supervising the hand removal and raking over of the top soil and rubble within the identified reptile areas. Once the material has been disturbed and checked for reptiles it will either be placed in a secure metal container and removed from site or compacted down and made unsuitable for reptiles. The careful removal of the top soil and natural refugia will allow the supervising ecologist chance to spot any reptiles which may be in danger and then remove them from the works area to a secure holding box and then the agreed translocation site. 3
4 The raked over soil will be compacted back down once the supervising ecologist is satisfied there are no reptiles present in the material. Any reptiles that are found during the supervised destructive searching will be captured by the supervising ecologist. The captured reptiles will be kept in a secure ventilated container and then removed to the agreed translocation site. A suitable translocation site has been agreed with the Ecologists at Caerphilly County Borough Council. Trehir Tip, Llanbradach located at NGR ST is the agreed translocation site. Any reptiles found at the proposed development site will be relocated and released at this site. A record of any reptiles found will be sent to the County Ecologists at Caerphilly County Borough Council. The ecologist will inform the applicant in writing when the site is considered to be clear of reptiles. A reptile hibernacula will be created at the translocation site. It will be built on a south facing slope in an undisturbed area of habitat agreed with the supervising ecologist. The hibernacula will measure 1.5m by 1.5m and will be at least 0.5m deep. It will be filled in layers of rubble and vegetated matter such as brash and tree limbs. Once the hole is filled a layer of soil will be placed over the top and allowed to naturally re-vegetate, it will not be reseeded. If the ground is to rocky to dig the required depth, a raised hiberacular will be constructed similar to the following drawing. 4
5 Appendix 1 Site Photographs Grassland in North East corner of site View of site looking east 5
6 View of raised garden area Numerous natural refugia in garden area 6
REPTILE TRANSLOCATION REPORT. Hoggett s End, Bishop s Stortford, Hertfordshire
REPTILE TRANSLOCATION REPORT Hoggett s End, Bishop s Stortford, Hertfordshire OCTOBER 2012 Surveyors: Peter Oakenfull AIEEM Date of Surveys: 30 th August 28 th September 2012 Report compiled by Graham
More informationA REPTILE SURVEY AT THE LAND AT HILL ROAD AND ELM TREE DRIVE, ROCHESTER, KENT,
A REPTILE SURVEY AT THE LAND AT HILL ROAD AND ELM TREE DRIVE, ROCHESTER, KENT, Commissioned by: King & Johnston Homes Ltd and Medway Council Report Number: October 2013 Regent s Place, 3 rd Floor, 338
More informationReptile Method Statement
, Northamptonshire A Report on behalf of March 2013 M1 CONTENTS 1.0 Introduction 1.1 Purpose of this Method Statement 1.2 Site Background 1.3 Reptile Ecology & Legal Protection 2.0 Methodology 2.1 Tool
More informationAppendix 6.4. Reptile Survey
Appendix 6.4 Reptile Survey University of Reading Whiteknights Campus Reptile Survey 2008 Prepared by:, Oxford July 2008 Mallams Court 18 Milton Park Abingdon Oxon OX14 4RP Tel 01235 821888 Fax 01235 820351
More informationMr T.B Brown. Land off Turweston Road, Northamptonshire REPTILE SURVEY REPORT
Mr T.B Brown Land off Turweston Road, Northamptonshire REPTILE SURVEY REPORT June 2013 FPCR Environment and Design Ltd Registered Office: Lockington Hall, Lockington, Derby DE74 2RH Company No. 07128076.
More informationPadgbury Lane North, Congleton REPTILE MITIGATION STRATEGY
Padgbury Lane North, Congleton REPTILE MITIGATION STRATEGY February 2014 FPCR Environment and Design Ltd Registered Office: Lockington Hall, Lockington, Derby DE74 2RH Company No. 07128076. [T] 01509 672772
More informationVIRIDOR WASTE MANAGEMENT LIMITED. Parkwood Springs Landfill, Sheffield. Reptile Survey Report
VIRIDOR WASTE MANAGEMENT LIMITED Parkwood Springs Landfill, Sheffield July 2014 Viridor Waste Management Ltd July 2014 CONTENTS 1 INTRODUCTION... 1 2 METHODOLOGY... 3 3 RESULTS... 6 4 RECOMMENDATIONS
More informationHallam Land Management, Taylor Wimpey UK Ltd, William Davis, Connolly Homes and. Bellcross Homes. South West Milton Keynes REPTILE REPORT
Hallam Land Management, Taylor Wimpey UK Ltd, William Davis, Connolly Homes and Bellcross Homes South West Milton Keynes REPTILE REPORT November 2014 FPCR Environment and Design Ltd Registered Office:
More informationLITTLE ACRE 80 THE STREET KENNINGTON ASHFORD KENT: REPTILES
LITTLE ACRE 80 THE STREET KENNINGTON ASHFORD KENT: REPTILES BY MARTIN NEWCOMBE 4 th August 2014 D96. Ashford (TR02294505) R2 Martin Newcombe Wildlife Management Consultancy 01233 720229 Page 1.0 INTRODUCTION
More informationLAND AT REAR OF PARAPET HOUSE LENHAM KENT REPTILE SCOPING SURVEY
LAND AT REAR OF PARAPET HOUSE LENHAM KENT REPTILE SCOPING SURVEY BY MARTIN NEWCOMBE 5 th June 2015 D100. Lenham (TQ8961152288).R2 Martin Newcombe Wildlife Management Consultancy 01233 720229 Page 1.0 INTRODUCTION
More informationDerwent Forest Reptile Survey Report. November 2009
Capita Blackburn Business Centre, CastleWay House, 17 Preston New Road, Blackburn BB2 1AU Tel 01254 273000 Fax 01254 273559 www.capitasymonds.co.uk Capita Symonds Ltd www.capitasymonds.co.uk Quality Management
More informationTeynham, Sittingbourne,, Kent. Reptile Survey. 02 nd October 2015 / Ref No 2015/07/13 Client: Hobbs Parker Property Consultants LLP
Teynham, Sittingbourne,, Kent 02 nd October 2015 / Ref No 2015/07/13 Client: Hobbs Parker Property Consultants LLP Prepared by Katia Bresso CEnv MCIEEM Trading as KB Ecology Ltd (Reg 7595382) 42, Douglas
More informationNative British Reptile Species
Lowland Derbyshire & Nottinghamshire LBAP Forum October 2008 Reptile Workshop Chris Monk Derbyshire Amphibian and Reptile Group Introductions Your knowledge / experience of reptiles and what extra you
More informationAppendix 8.5 Reptile Survey Report
Appendix 8.5 Reptile Survey Report Abergelli Power Project Reptile Survey Report Abergelli Power Limited November 2017 Document Control Document Properties Organisation Author Approved by 1 st checker)
More informationBritish Reptiles. By Sue Searle
British Reptiles By Sue Searle What is a reptile? Back-bone present Cold-blooded. Inactive in winter Scaly skin which is shed No water required for mating or young Most lay eggs but some are viviparous
More information9. Creating Reptile Habitat Features
9. Creating Reptile Habitat Features 9.1. Brash and log piles The value of brash and log piles lies in; creating cover, providing additional structure to existing habitat, enhancing prey availability.
More informationAppendix 10.1g Extension Area Reptile Survey Report
Appendix 10.1g Extension Area Reptile Survey Report On behalf of E & JW Glendinning Ltd. MARCH 2016 CONTENTS 1.0 INTRODUCTION... 2 1.1 OVERVIEW & SURVEY OBJECTIVES... 2 1.2 CONSERVATION STATUS & PROTECTION...
More informationHOW DID THE ADDER BECOME EXTINCT IN WARWICKSHIRE? Jan Clemons Warwickshire Amphibian & Reptile Team (WART)
HOW DID THE ADDER BECOME EXTINCT IN WARWICKSHIRE? Jan Clemons Warwickshire Amphibian & Reptile Team (WART) THE WARWICKSHIRE ADDER HUNT In 2004 WART became the lead partner for the adder in the Warwickshire,
More informationReptile Survey. Boverton, Vale of Glamorgan. For. Barratt Homes South Wales. Project No.: ABAW105 / 007. May
For Barratt Homes South Wales Project No.: ABAW105 / 007 May 2015 www.thomsonecology.com London & South East Compass House Surrey Research Park Guildford GU2 7AG. UK t: +44 (0)1483 466 000 North & Borders
More information7550: THE PLOUGH INN, BRABOURNE LEES, KENT BRIEFING NOTE: KCC ECOLOGY RESPONSE 17/01610/AS
Cokenach Estate Bark way Royston Hertfordshire SG8 8DL t: 01763 848084 e: east@ecologysolutions.co.uk w: www.ecologysolutions.c o.uk 7550: THE PLOUGH INN, BRABOURNE LEES, KENT BRIEFING NOTE: KCC ECOLOGY
More informationThe effectiveness of reptile exclusion techniques as revealed by photorecognition
The effectiveness of reptile exclusion techniques as revealed by photorecognition Dr Liam Russell CEcol MCIEEM (Russell Ecology & ARC Ecological Services Ltd) Jim Foster MCIEEM (ARC Ecological Services
More informationReptile Survey Report
P O R T I S H E A D B R A N C H L I N E P R E L I M I N A R Y ENV I R O N M E N T A L I N F O R M A T I O N R E P O R T V O L U M E 4 A P P E N D I X 9. 5 Reptile Survey Report Table of Contents Section
More informationReptile Survey. St Michael's Church, Dalston, Carlisle, Cumbria, CA5 7LN 2012
Reptile Survey St Michael's Church, Dalston, Carlisle, Cumbria, CA5 7LN Report commissioned by: Dalston Parish Council Forge Green Dalston Carlisle Cumbria CA5 7QG Report compiled by: Sam Griffin Cumbria
More informationPioneer Dairy Wetlands
Pioneer Dairy Wetlands Eastern Long-necked Turtle Green and Golden Bell Frog DRAFT Master plan June 2011 1 Contents WHS contribution 3 Location for Enclosure and Rehabilitation area 4 Eastern Long-necked
More informationTHE LAWNS CEMETERY 1 FILEY TOWN COUNCIL
Page 1 FILEY TOWN COUNCIL THE LAWNS CEMETERY Regulations & Conditions The Lawns Cemetery, Padbury Avenue, Filey, North Yorkshire. OCTOBER 2015 Page 2 Contents Introduction Page 3 Administration Page 4
More informationUrbanization Activity
Grade 9- Human-Environment Interactions Activity Urbanization Activity for Grade 9 Geography at the Toronto Zoo ZOO ACTIVITY: ANIMALS AND URBANIZATION Time Needed: Actual write-up should take well under
More informationWater vole survey on Laughton Level via Mill Farm
Water vole survey on Laughton Level via Mill Farm Grid reference: TQ 4911 Mill Farm, Ripe, East Sussex November 2008 Hetty Wakeford Ecologist Sussex Ecology Introduction The Ecologist undertook a water
More informationAmphibians & reptiles. Key points
Grass snake Ian McIntosh CC BY SA 3.0 Amphibians & reptiles Amphibians and reptiles are highly charismatic creatures and an important part of Britain s natural and cultural history. Over recent decades,
More informationRegulating the scientific use of animals taken from the wild Implementation of Directive 2010/63/EU
Regulating the scientific use of animals taken from the wild Implementation of Directive 2010/63/EU Dr Kim Willoughby, Mr Peter Gray, Dr Kate Garrod. Presented by: Dr Kim Willoughby Date: 26 October 2017
More informationPIGEON MAGNET INSTRUCTION MANUAL
THE PIGEON MAGNET INSTRUCTION MANUAL Version 1. November 2012 Code 07-Trap10 Product Pigeon Magnet Trap Optional Accessories (sold separately): 07-trap9c Pigeon Magnet Storage Bag 07-trap9f Pigeon Magnet
More informationA MODEL TOWNSHIP ZONING ORDINANCE: RAISING AND KEEPING OF CHICKENS 1
The following model zoning ordinance may be used as a basis for municipal regulation of noncommercial and small-scale keeping of chickens. The municipal zoning ordinance is generally the best location
More informationNATIONAL COUNCIL OF SPCAs SPECIAL PROJECTS UNIT
NATIONAL COUNCIL OF SPCAs SPECIAL PROJECTS UNIT HUMANE DETERRENTS AND PEST CONTROL: RODENTS - 2014 1. RODENT CONTROL FOREWORD While the National Council of SPCAs (NSPCA) acknowledges that under certain
More informationCITY OF WHITEHALL OAKHURST CEMETERY RULES AND REGULATIONS (Adopted by Resolution 98-96)
CITY OF WHITEHALL OAKHURST CEMETERY RULES AND REGULATIONS (Adopted by Resolution 98-96) For mutual protection of lot owners and the cemetery as a whole, the following rules and regulations have been adopted
More informationPEREGRINE FALCON HABITAT MANAGEMENT GUIDELINES ONTARIO MINISTRY OF NATURAL RESOURCES
PEREGRINE FALCON HABITAT MANAGEMENT GUIDELINES ONTARIO MINISTRY OF NATURAL RESOURCES December 1987 2 Table of Contents Page Introduction...3 Guidelines...4 References...7 Peregrine Falcon Nest Site Management
More informationProperty and infrastructure 1. INTRODUCTION. 1.1 Background. 1.2 Survey Site. Date
Date 06-6-2018 Tamara Lanoix Unit 1a, Vantage House Vantage Park Washingley Road Huntingdon Cambs PE29 6SR Dear Tamara Subject Water Vole Survey Results - Chesterton Bridge 1. INTRODUCTION 1.1 Background
More informationWhat is the date at which most chicks would have been expected to fledge?
CURLEW FAQs FACTS AND FIGURES AND ADVICE FOR THOSE WANTING TO HELP SUPPORT NESTING CURLEW ON THEIR LAND The Eurasian Curlew or, Numenius arquata, spends much of the year on coasts or estuaries, but migrates
More information1. Aims. 2. Introduction
Adder John Archer The gardeners employed at villas close to the metropolis occasionally raise an alarm, and profess to have seen a viper in the shrubberies... (Jefferies, 1893). 1. Aims To protect and
More informationLLWR Ecology Framework
LLWR Ecology Framework Reptile Survey 47058923 NTRP0014 Prepared for: LLWR UNITED KINGDOM & IRELAND Rev Date Details Prepared by Checked by Approved by 1 19.10.12 Original Submission Darryn Nash Senior
More informationWater Vole Translocation Project: Abberton ReservoirAbout Water Voles Population Dynamics
Water Vole Translocation Project: Abberton ReservoirAbout Water Voles Measuring up to 24cm, water voles (Arvicola amphibius) are the largest of the British voles and at a quick glace, are often mistaken
More informationAppendix 8.B Great Crested Newt Survey Report
Appendix 8.B Great Crested Newt Survey Report Entec UK Limited Entec UK Limited Kelmarsh Windfarm, Northamptonshire Great Crested Newt Survey Report June 2008 Client Job Name Report title File reference
More informationSquamates of Connecticut
Squamates of Connecticut Reptilia Turtles are sisters to crocodiles and birds Yeah, birds are reptiles, haven t you watched Jurassic Park yet? Lizards and snakes are part of one clade called the squamates
More informationDesign Guide. You can relax with a INSTALLATION QUALITY,CERTIFIED QTANK POLY RAINWATER TANKS. qtank.com.au
INSTALLATION Design Guide A division of QSolutions Co POLY RAINWATER TANKS You can relax with a QUALITY,CERTIFIED QTANK qtank.com.au sales@qsolutionsco.com.au (07) 3881 0208 THE FOLLOWING GUIDELINES APPLY
More informationCllrs Faulkner (Chair), Fleming, Hale, Robinson-Giannasi and Stewart
MINUTES OF THE MEETING OF ODIHAM PARISH COUNCIL S PLANNING AND DEVELOPMENT COMMITTEE HELD IN THE PARISH ROOM, THE BURY, ODIHAM ON MONDAY 18 FEBRUARY 2019 COMMENCING AT 7.30 PM Present: Also present: Cllrs
More informationExplanatory Memorandum to the Mutilations (Permitted Procedures) (Wales) (Amendment) Regulations 2008
Explanatory Memorandum to the Mutilations (Permitted Procedures) (Wales) (Amendment) Regulations 2008 This Explanatory Memorandum has been prepared by the Office of the Chief Veterinary Officer and is
More informationReport to the Raleigh Parks, Recreation and Greenway Advisory Board: Off-leash Dog Areas. Background
1 Report to the Raleigh Parks, Recreation and Greenway Advisory Board: Off-leash Dog Areas Report by Ad Hoc Committee: Jan Kirschbaum, Wayne Marshall, Gail Till, Bill Hornsby (P.U.P) January 20, 2005 Background
More informationInhumane Handling. Can happen at any point in the catching process, especially at:-
Brian Faulkner Inhumane Handling Can happen at any point in the catching process, especially at:- Point of capture. Movement onto and off vehicles. Within the holding facility. Main causes are Untrained
More informationReptile Identification Guide
Care & preservation of Surrey s native amphibians and reptiles Reptile Identification Guide This identification guide is intended to act as an aid for SARG surveyors. Adder, Vipera berus A short, stocky
More informationGreenham Common, Crookham Common and Bowdown Wood Reptile Survey 2010
Greenham Common, Crookham Common and Bowdown Wood Reptile Survey 2010 Rod d Ayala and Martin Burdock, November 2010 CONTENTS Text Executive Summary Page 3 Background Page 4 Survey Methods, Personnel and
More informationItem No: 3 Reference: B/16/00999/FUL. Parish: SHOTLEY Ward Members: Cllrs. Peter Patrick and Derek Davis
Item No: 3 Reference: B/16/00999/FUL Parish: SHOTLEY Ward Members: Cllrs. Peter Patrick and Derek Davis Proposal: Location: Applicant: Change of use of dwelling (Class C3) to mixed use C3 (dwelling) and
More informationAbout GOTBA Vic. Yours sincerely. The Executive Committee. Greyhound Owners, Trainers and Breeders Association of Victoria Inc.
Reg No: A0017661V ABN: 67 306 599 068 Greyhound Owners, Trainers and Breeders Association of Victoria Inc (GOTBA Vic) Submission on Guidelines for Racing Dog Keeping and Training Facilities (2016) About
More informationChapter 190 URBAN CHICKEN
Chapter 190 URBAN CHICKEN ARTICLE I Title, Legislative Findings, and Authority 190-1. Short title. 190-2. Findings. 190-3. Statutory authority. ARTICLE II Definitions 190-4. Definitions. ARTICLE III Permitting
More informationPUBLIC SPACES PROTECTION ORDERS DOG CONTROLS CULTURE AND LEISURE (COUNCILLOR PETER BRADBURY)
CARDIFF COUNCIL CYNGOR CAERDYDD CABINET MEETING: 12 JULY 2018 PUBLIC SPACES PROTECTION ORDERS DOG CONTROLS CULTURE AND LEISURE (COUNCILLOR PETER BRADBURY) AGENDA ITEM: 3 Reason for this Report 1. To consider
More informationCommunity Cats. Tips to keep your Community Cats away from your property. Adopted from Neighborhood Cats TNR Handbook 2 nd Edition
Community Cats Tips to keep your Community Cats away from your property Adopted from Neighborhood Cats TNR Handbook 2 nd Edition Note: This information is an excerpt from Neighborhood Cats TNR Handbook
More informationRULES AND REGULATIONS. For the PRINCETON CEMETERY. Of the NASSAU PRESBYTERIAN CHURCH
RULES AND REGULATIONS For the PRINCETON CEMETERY Of the NASSAU PRESBYTERIAN CHURCH ****************************************** Please retain these Rules and Regulations for future reference In connection
More informationSOSSAMAN CLOUD PARK. Site Conditions
SOSSAMAN CLOUD PARK distant views of the Superstition Mountains to the northeast. A series of dirt roads are visible throughout the site and trash and debris from local neighborhoods are present. A graded
More informationCOUNTRY LEGISLATION GIVING PROTECTION SCHEDULE OR
Technical Guidance Series In association with Competencies for Species Survey: www.cieem.net 1. Introduction The purpose of this document is to set out the knowledge, skills and experience required to
More informationNaturalised Goose 2000
Naturalised Goose 2000 Title Naturalised Goose 2000 Description and Summary of Results The Canada Goose Branta canadensis was first introduced into Britain to the waterfowl collection of Charles II in
More informationFrom mountain to sea. A Survivor s Guide to Living with Urban Gulls
From mountain to sea A Survivor s Guide to Living with Urban Gulls 1 The Gull Problem Growing numbers of Lesser Black-backed and Herring gulls now build nests on the roofs of homes and businesses in towns
More informationK E N N E L L I C E N S E A P P L I C A T I O N
T O W N S H I P O F N O R T H G L E N G A R R Y K E N N E L L I C E N S E A P P L I C A T I O N Date: Name of Applicant: Applicant Address: Home Phone: Other Number: Location of proposed Kennel facility:
More informationAn Invasive Species For more information: MyFWC.com/iguana
An Invasive Species The green iguana (Iguana iguana) is a large lizard not native to Florida. Florida s subtropical climate has allowed these iguanas to thrive and reproduce in regions of the state where
More informationOVER 30 MONTH CATTLE SLAUGHTER RULE (OTM Rule)
BACKGROUND FSA REVIEW OF BSE CONTROLS OVER 30 MONTH CATTLE SLAUGHTER RULE (OTM Rule) THE RULE 1. The Over 30 Month Rule, with some exceptions, prohibits the sale of meat for human consumption from cattle
More informationAUGUST 2016 Ashford Park Quarry Pest Plant and Animal Control Plan
AUGUST 2016 Ashford Park Quarry Pest Plant and Animal Control Plan This Pest Plant and Animal Control Plan has been developed for the Ashford Park Quarry, Otaki as required by Conditions 43 and 44 of the
More informationSlater M. (2007) 149 Norton Leys, Rugby CV22 5RS, UK SUMMARY
Creation of a drystone wall to create egglaying habitat for grizzled skipper Pyrgus malvae at Ryton Wood Meadows Butterfly Conservation Reserve, Warwickshire, England Slater M. (2007) 149 Norton Leys,
More informationIMPORT HEALTH STANDARD FOR ZOO CROCODILIA FROM AUSTRALIA
IMPORT HEALTH STANDARD FOR ZOO CROCODILIA FROM AUSTRALIA Issued pursuant to Section 22 of the Biosecurity Act 1993 Dated: 21 April 2008 USER GUIDE The information in MAFBNZ animal and animal product import
More informationBromyard Downs Reptile Survey April - August 2014
Nigel Hand Central Ecology 45 Albert Road Ledbury Herefordshire HR8 2DN 01531 636033 Bromyard Downs Reptile Survey April - August 2014 Commissioned by Bromyard Downs Project Herefordshire Nature Trust
More informationEndangered Plants and Animals of Oregon
))615 ry Es-5- Endangered Plants and Animals of Oregon H. Amphibians and Reptiles Special Report 206 January 1966 1,9 MAY 1967 4-- 1=3 LPeRARY OREGON ctate CP tffirversity Agricultural Experiment Station
More informationBARRY KEMP CONSERVATION LIMITED ʻAmblehurstʼ Nevill Road Crowborough East Sussex TN6 2RA
MARKSTAKES COMMON SNCI REPTILE SURVEY FOR LEWES DISTRICT COUNCIL MARCH 2013 BARRY KEMP CONSERVATION LIMITED ʻAmblehurstʼ Nevill Road Crowborough East Sussex TN6 2RA (t) 01892 663942 (m) 07780 665177 (e)
More informationAvoiding Snakes and Spiders
August 2013 2013 PLANET Editor s note: PASS ON EACH ISSUE OF THIS NEWSLETTER TO EVERYONE WITH SAFETY RESPONSIBILITIES AT YOUR COMPANY. Avoiding Snakes and Spiders Note: This is the second newsletter in
More informationDON T FALL FOWL OF THE WILDLIFE LAW. By Andrew Cowan N.D.Arb. November 2002 A & E. ArborEcology. Arboricultural & Ecological Research & Consultants
By Andrew Cowan N.D.Arb. A & E ArborEcology Arboricultural & Ecological Research & Consultants DON T FALL FOWL OF WILDLIFE LAW As the onset of spring and the rising sap means tree pruning has to stop for
More informationORDINANCE NO
ORDINANCE NO. 590-19 BOROUGH OF ATGLEN CHESTER COUNTY, PENNSYLVANIA AN ORDINANCE AMENDING THE ATGLEN BOROUGH ZONING ORDINANCE TO PROVIDE FOR AND REGULATE THE RAISING AND KEEPING OF DOMESTICATED CHICKENS
More informationAdd my to the License and Permits Listserv so that I can receive updates regarding licenses, rules changes, etc.
PERMIT APPLICATION CONDITIONAL/PROHIBITED/NONNATIVE SPECIES FLORIDA FISH AND WILDLIFE CONSERVATION COMMISSION Division of Habitat and Species Conservation, Exotic Species Coordination Section 620 S. Meridian
More informationSouthborough Town Council. Burial Ground Regulations
Southborough Town Council Burial Ground Regulations 1. Introduction 1.1. These regulations apply to all burial grounds owned and/or managed by Southborough Town Council. Currently the sites include: Southborough
More informationWFN DOG AND CAT CONTROL LAW NO DOG AND CAT FEE SCHEDULE. FORM A (Section 3.14)
DOG AND CAT FEE SCHEDULE FORM A (Section 3.14) Type of Application Section of Law Fee Amount LICENSING Spayed female or neutered male dog, upon 3.5 production of written proof Unspayed female or unneutered
More informationIn the matter of the Resource Management Act 1991 MERIDIAN ENERGY LIMITED. Applicant. HURUNUI DISTRICT COUNCIL and CANTERBURY REGIONAL COUNCIL
IN THE ENVIRONMENT COURT CHRISTCHURCH REGISTRY In the matter of the Resource Management Act 1991 ENV-2011-CHC-090 Between MERIDIAN ENERGY LIMITED Applicant And HURUNUI DISTRICT COUNCIL and CANTERBURY REGIONAL
More informationTrack & Search Dog Information for Judges
Track & Search Dog Information for Judges The purpose of these tracks is to give dogs the opportunity to train and track in a more real-life manner. There is a world of difference in the way an Operational
More informationATTACHMENT NO. 35 ENDANGERED SPECIES PROTECTION PLAN
ATTACHMENT NO. 35 ENDANGERED SPECIES PROTECTION PLAN ATTACHMENT NO. 35 ENDANGERED SPECIES PROTECTION PLAN The following conservation measures will be implemented in order to protect endangered species
More information10/03/18 periods 5,7 10/02/18 period 4 Objective: Reptiles and Fish Reptile scales different from fish scales. Explain how.
10/03/18 periods 5,7 10/02/18 period 4 Objective: Reptiles and Fish Reptile scales different from fish scales. Explain how. Objective: Reptiles and Fish Reptile scales different from fish scales. Explain
More informationAppendix 8.18 Reptile Survey Report 2014
Appendix 8.18 Reptile Survey Report 2014 Abergelli Abergelli Power Project Reptile Survey Report BLANK PAGE 2 10/03/2015 Issuing office Wyastone Business Park Wyastone Leys Monmouth NP25 3SR T: 01600 891576
More informationBuilding shelters for lizards and snakes
Building shelters for lizards and snakes By Daniel Guérineau and Loïc Brepson Build shelters for lizards and snakes November 2016 1 Why build shelters? Reptiles are ectothermic : their temperature varies
More informationReptile Survey of Hampstead Heath
Appendix 1 London Essex and Hertfordshire Amphibian and Reptile Trust (Registered Charity Number: 1089466) Reptile Survey of Hampstead Heath 2008-2009 Grass Snake on Hampstead Heath Will Atkins, LEHART
More informationNorthumbrian Water Reptile Survey Report Volume 1: Northern Area
Northumbrian Water Volume 1: Northern Area August 2007 Final Client Job Name Report title File reference Northumbrian Water Ltd Reptile Surveys 2432_n007_fin rep_jt_mm.doc Signed Name Position Date Originated
More informationAbout Reptiles A Guide for Children. Cathryn Sill Illustrated by John Sill
About Reptiles About Reptiles A Guide for Children Cathryn Sill Illustrated by John Sill For the One who created reptiles. Genesis 1:24 Published by PEACHTREE PUBLISHERS, LTD. 1700 Chattahoochee Avenue
More informationOutcomes of the Hazelmere Reserve Community Survey
Outcomes of the Hazelmere Reserve Community Survey In October 2012, a community survey was mailed to 955 residents within a 400m radius of Hazelmere Reserve, as an evaluation of the playground upgrade.
More information1.0 SUMMARY OF THE ACTIVITY UNDERTAKEN TO PROTECT AND ENHANCE THE ENVIRONMENT: PROJECT OBJECTIVES, SOLUTIONS AND ACHIEVEMENTS
EXECUTIVE SUMMARY Blanding s Turtles nest in the granular shoulders of roadways, burying eggs beneath the ground surface. Visual detection of nests is not possible. Highway rehabilitation can damage or
More informationMelbourne Water Corporation. Sheoak Striped Legless Lizard, Golden Sun Moth and Vegetation Monitoring Project Striped Legless Lizard Monitoring
Melbourne Water Corporation Sheoak Striped Legless Lizard, Golden Sun Moth and Vegetation Monitoring Project Striped Legless Lizard Monitoring February 04 Table of contents. Introduction.... Introduction....
More informationCity of Brampton Draft Licensing By-law
SCHEDULE 16 TO BY-LAW # RELATING TO KENNELS, PET BOARDING AND PET DAYCARE FACILITIES 1. In this Schedule: Animal means a dog, cat or any other pet that is generally understood to be domesticated and is
More informationTITLE XVII HUNTLEY CEMETERY GUIDELINES. Updated and Approved Ordinance (O)
TITLE XVII HUNTLEY CEMETERY GUIDELINES Updated and Approved Ordinance (O)2012-12.75 TITLE XVII: HUNTLEY CEMETERY GUIDELINES Chapter 170. CEMETERY GUIDELINES 171. COLUMBARIUM GUIDELINES Section CHAPTER
More informationPE1561/J. Ned Sharratt Public Petitions Clerks Room T3.40 The Scottish Parliament Edinburgh EH99 1SP. 11 December 2015.
PE1561/J Agriculture, Food and Rural Communities Directorate Animal Health and Welfare Division T: 0300-244 9242 F: 0300-244 E: beverley.williams@scotland.gsi.gov.uk Ned Sharratt Public Petitions Clerks
More informationNational status and trends of adders in Britain. Angela Julian & John Baker (ARG UK), Jim Foster (ARC)
National status and trends of adders in Britain Angela Julian & John Baker (ARG UK), Jim Foster (ARC) National & Regional Status Cooke, A.S. & Scorgie, H.R.A. (1983). The status of the commoner amphibians
More informationNest Site Creation and Maintenance as an Effective Tool in Species Recovery
Nest Site Creation and Maintenance as an Effective Tool in Species Recovery Scott D. Gillingwater Species At Risk Biologist Upper Thames River Conservation Authority Where and Why? The successful creation
More informationGeneral Licence for the Movement of Cattle
General Licence for the Movement of Cattle In accordance with Article 12 of the Disease Control (Wales) Order 2003 (as amended) (the "Disease Control Order") 1 the Welsh Ministers hereby authorise by this
More informationTitle of Project: Distribution of the Collared Lizard, Crotophytus collaris, in the Arkansas River Valley and Ouachita Mountains
Title of Project: Distribution of the Collared Lizard, Crotophytus collaris, in the Arkansas River Valley and Ouachita Mountains Project Summary: This project will seek to monitor the status of Collared
More informationHEALTHY TONGA TOURISM A GUIDE TO CONTROLLING MOSQUITO-BORNE DISEASES FOR TOURIST ACCOMMODATION BUSINESSES IN TONGA
HEALTHY TONGA TOURISM A GUIDE TO CONTROLLING MOSQUITO-BORNE DISEASES FOR TOURIST ACCOMMODATION BUSINESSES IN TONGA Contents 1. Purpose of guide 1 2. Vector-borne diseases and control planning 1 Mosquito
More informationTHE CONFERENCE OF THE PARTIES TO THE CONVENTION
Conf. 12.10 (Rev. CoP15)* Registration of operations that breed Appendix-I animal species in captivity for commercial purposes RECALLING Resolution Conf. 8.15, adopted by the Conference of the Parties
More informationSnapping Turtle Monitoring Program Guide
Snapping Turtle Monitoring Program Guide Table of Contents 1.0 The Snapping Turtle... 3 1.1 Description... 3 1.2 Distribution and Habitat... 3 1.3 Status and Threats... 3 1.4 Reproduction and Nesting...
More informationTurtle Mitigation for Road and Highway Projects Pembroke District MNR Interim Guidelines Version 1.0 (April 2014)
Turtle Mitigation for Road and Highway Projects Pembroke District MNR Interim Guidelines Version 1.0 (April 2014) Photo: Gerald Rollins Draft Turtle Mitigation for Road and Highway Projects Pembroke District
More informationBest Practice on the Farm
Best Practice on the Farm Rodent Control Best Practice on the Farm Rodent Control Introduction Rodents carry diseases which can contaminate a poultry flock; however, preventing rodents on a farm can be
More informationA Study to Determine the Preference for Nesting Box Design of Sialia sialis
A Study to Determine the Preference for Nesting Box Design of Sialia sialis (Eastern Bluebird): Comparison of the Traditional Nesting Box and the Peterson Box Year 2 C. A. Burkart 1, A. Russo 1, C. Meade
More informationEUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY
Ref. Ares(2018)2119965-20/04/2018 EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY Health and food audits and analysis DG(SANTE) 2017-6296 FINAL REPORT OF AN AUDIT CARRIED OUT IN DENMARK
More informationAmrun Project Feral Animal Monitoring Annual Report August 2017
Amrun Project Feral Animal Monitoring Annual Report August 2017 A report prepared in accordance with requirements of the Amrun Project EPBC Act Approval 2010/5642, Terrestrial Management Plan, Construction
More information